- Q1 Past Paper · PPSC/FPSC/NTS hard
8 men and 4 women together can complete a piece of work in 6 days. Work done by a man in one day is twice that of a woman. After 2 days, 4 men left and 4 new women joined. In how many days will the work be completed
💡 Explanation:Team rate 20w=1/6; after 2 days 1/3 done, new team rate 16w=2/15 finishes remaining 2/3 in 5 days, total 7 days.
- Q2 Past Paper · PPSC/FPSC/NTS hard
2 men and 3 women can do a piece of work in 10 days, while 4 men and 3 women can do the same work in 8 days. In how many days will 10 women do it
💡 Explanation:Solving gives man rate=1/80, woman rate=1/40; 10 women rate=1/4, so 4 days.
- Q3 Past Paper · PPSC/FPSC/NTS hard
A, B and C can do a piece of work in 12 days, 15 days and 20 days respectively working alone. They started working together but C left 2 days before completion. In how many days was the work completed
💡 Explanation:(x-2)/5 + 2(3/20) = 1 gives x-2=3.5, so x = 5.5 days.
- Q4 hard
A and B can do a piece of work in 12 days, B and C in 15 days and C and A in 20 days. In how many days will A, B and C finish the work together
💡 Explanation:Sum of pairs = 2(A+B+C) = 1/5, so A+B+C = 1/10, giving 10 days.
- Q5 Past Paper · PPSC/FPSC/NTS medium
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is
💡 Explanation:Tanya's rate = 1.25/20 = 1/16, so 16 days.
- Q6 Past Paper · PPSC/FPSC/NTS medium
A can do a piece of work in 24 days. If B is 60% more efficient than A, how many days would B take to do the same job
💡 Explanation:B's rate = 1.6/24 = 1/15, so B takes 15 days.
- Q7 hard
A does 4/5 of a work in 20 days. He then calls in B and they finish the remaining work in 3 days. How long would it take B to do the whole work alone
💡 Explanation:A's rate = 1/25; combined does 1/5 in 3 days, so B's rate = 2/75, taking 37.5 days.
- Q8 easy
45 men can do a work in 20 days. How many men would be needed to complete the same work in 15 days
💡 Explanation:Total work = 900 man-days; men needed = 900/15 = 60.
- Q9 Past Paper · PPSC/FPSC/NTS easy
A can do a piece of work in 12 days and B can do it in 18 days. In how many days will they finish it together
💡 Explanation:Combined rate = 1/12+1/18 = 5/36, so time = 36/5 = 7.2 days.
- Q10 Past Paper · PPSC/FPSC/NTS easy
A alone can complete a job in 15 days, B alone in 10 days. If they work together, in how many days will the job be completed
💡 Explanation:Combined rate = 1/15+1/10 = 1/6, so time = 6 days.
- Q11 medium
A can finish a work in 20 days and B in 25 days. They work together for 5 days and then A leaves. In how many days will B finish the remaining work
💡 Explanation:Work done in 5 days = 9/20, remaining 11/20 taken by B alone = 11/20 divided by 1/25 = 13.75 days.
- Q12 Past Paper · PPSC/FPSC/NTS easy
4 men can complete a work in 12 days. How many men are required to complete the work in 8 days
💡 Explanation:Men x days is constant: 4x12=48, so men = 48/8 = 6.
- Q13 medium
A and B together can complete a work in 8 days. A alone can do it in 12 days. In how many days can B alone complete it
💡 Explanation:1/B = 1/8-1/12 = 1/24, so B alone takes 24 days.
- Q14 Past Paper · PPSC/FPSC/NTS easy
6 women can complete a piece of work in 10 days. In how many days will 15 women complete the same work
💡 Explanation:Total work = 60 women-days; with 15 women, time = 60/15 = 4 days.
- Q15 medium
A can do a work in 9 days, B in 12 days and C in 18 days. Working together, in how many days will they complete the work
💡 Explanation:Combined rate = 1/9+1/12+1/18 = 1/4, so time = 4 days.
- Q16 medium
A is twice as efficient as B. If B alone can complete a work in 24 days, in how many days can A and B together complete it
💡 Explanation:A rate = 1/12, B rate = 1/24, combined = 1/8, so 8 days.
- Q17 Past Paper · PPSC/FPSC/NTS medium
A tank can be filled by pipe A in 6 hours and emptied by pipe B in 9 hours. If both pipes are opened together, in how many hours will the tank be filled
💡 Explanation:Net rate = 1/6-1/9 = 1/18, so tank fills in 18 hours.
- Q18 Past Paper · PPSC/FPSC/NTS easy
Two pipes A and B can fill a tank in 20 and 30 minutes respectively. If both pipes are opened simultaneously, how long will it take to fill the tank
💡 Explanation:Combined rate = 1/20+1/30 = 1/12, so 12 minutes.
- Q19 medium
A pipe can fill a tank in 10 hours. Due to a leak in the bottom, it takes 12 hours to fill the tank. In how many hours can the leak alone empty the full tank
💡 Explanation:Leak rate = 1/10-1/12 = 1/60, so leak empties tank in 60 hours.
- Q20 Past Paper · PPSC/FPSC/NTS easy
Ten men can complete a piece of work in 15 days. How many men are needed to complete the work in 25 days
💡 Explanation:Total work = 150 man-days; men needed = 150/25 = 6.
- Q21 medium
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days will A alone finish the remaining work
💡 Explanation:B's work in 10 days = 2/3, remaining 1/3 done by A at rate 1/18, taking 6 days.
- Q22 Past Paper · PPSC/FPSC/NTS easy
A works twice as fast as B. If B can complete a work in 18 days independently, the number of days in which A and B can together finish the work is
💡 Explanation:A rate=1/9, B rate=1/18, combined=1/6, so 6 days.
- Q23 hard
P, Q and R can do a work in 20, 30 and 60 days respectively. P works with the help of Q and R on every third day. In how many days is the work completed
💡 Explanation:Each 3-day cycle completes 1/5 of the work; after 4 full cycles and 2 extra days the work finishes in 15 days.
- Q24 Past Paper · PPSC/FPSC/NTS hard
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is paid to C
💡 Explanation:C's rate = 1/3-7/24 = 1/24; C's work in 3 days = 1/8, so payment = 3200/8 = Rs. 400.
- Q25 medium
Twenty women can do a work in 16 days. Sixteen men can complete the same work in 15 days. What is the ratio between the capacity of a man and a woman
💡 Explanation:Total work: 320 women-days = 240 men-days, so man:woman = 320:240 = 4:3.
- Q26 Past Paper · PPSC/FPSC/NTS hard
A and B undertake to do a piece of work for Rs. 600. A alone can do it in 6 days while B alone can do it in 8 days. With the help of C, they finish it in 3 days. What is C's share
💡 Explanation:C's one-day rate = 1/3-7/24 = 1/24; in 3 days C does 1/8 of work, earning 600 x 1/8 = Rs. 75.
- Q27 medium
A can do a certain work in 12 days. B is 60% more efficient than A. How many days does B alone take to do the same work
💡 Explanation:B's rate = 1.6 x (1/12) = 2/15, so B takes 7.5 days.
- Q28 hard
Two workers A and B are engaged to do a work. A working alone takes 8 hours more than the time taken by A and B together. If B worked alone, he would take 4.5 hours more than the time taken together. Find the time taken by A and B together
💡 Explanation:Time together = sqrt(8 x 4.5) = sqrt(36) = 6 hours.
- Q29 Past Paper · PPSC/FPSC/NTS hard
A is thrice as good a workman as B and takes 10 days less to do a piece of work than B. In how many days will they together complete the work
💡 Explanation:B takes 15 days, A takes 5 days; combined rate = 4/15, so time = 3.75 days.
- Q30 hard
10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man alone to complete the same work. How many days will be required for one woman alone to complete the same work
💡 Explanation:15 women rate = 1/6-1/10 = 1/15, so one woman rate = 1/225, taking 225 days.
- Q31 hard
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days can A alone finish the work
💡 Explanation:Work done together in 20 days = 2/3, remaining 1/3 done by A in 20 days, so A alone takes 60 days.
- Q32 medium
A can complete a work in 20 days. He worked at it for 5 days and then B alone finished the remaining work in 15 days. In how much time will A and B together finish the work
💡 Explanation:B's rate = (3/4)/15 = 1/20, same as A; combined rate = 1/10, so 10 days.
- Q33 Past Paper · PPSC/FPSC/NTS medium
39 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons complete the work working 6 hours a day
💡 Explanation:Total person-hours = 2340; with 30 persons at 6 hrs/day, days = 2340/180 = 13.
- Q34 medium
A can do a work in 15 days. A worked for 3 days and then left. B finished the remaining work in 18 days. In how many days will A and B together complete the whole work
💡 Explanation:B's rate = (4/5)/18 = 2/45; combined with A's 1/15 gives 1/9, so 9 days.
- Q35 hard
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of work. How long did the work last
💡 Explanation:X alone does 1/5 in 4 days; remaining 4/5 at combined rate 2/15 takes 6 more days, totaling 10 days.
- Q36 Past Paper · PPSC/FPSC/NTS hard
A and B can do a piece of work in 15 days and 10 days respectively. They started working together but B left 5 days before completion. In how many days was the work completed
💡 Explanation:x/15+(x-5)/10=1 gives 5x=45, so x=9 days.
- Q37 hard
A can do a work in 25 days and B in 20 days. They started together, but A left after some days and B finished the remaining work in 10 days. After how many days did A leave
💡 Explanation:x/25+10/20=1 gives x/25=1/2, so x=12.5 days.
- Q38 medium
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work
💡 Explanation:Total work=720 man-days; 270 done in 6 days, remaining 450 man-days at 75 men = 6 days.
- Q39 Past Paper · PPSC/FPSC/NTS easy
A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work together
💡 Explanation:Combined rate = 1/4+1/12 = 1/3, so 3 days.
- Q40 hard
12 men can complete a work in 18 days. 6 men started the work and after 6 days, 6 more men joined. In how many more days will they complete the work
💡 Explanation:Total work = 216 man-days; 36 done in first 6 days, remaining 180 man-days at 12 men = 15 days.
- Q41 hard
A does half as much work as B in three-fourth of the time taken by B. If together they take 18 days to complete the work, how much time shall B take to do it alone
💡 Explanation:A's time for full work = 1.5 times B's time; combined rate 5/(3x)=1/18 gives x=30 days.
- Q42 medium
A works twice as fast as B. If both together can complete a work in 12 days, in how many days can A alone complete the work
💡 Explanation:Combined rate 3r=1/12 gives r=1/36; A's rate=2r=1/18, so A alone takes 18 days.
- Q43 medium
3 men or 5 women can do a work in 12 days. In how many days will 6 men and 5 women complete the work
💡 Explanation:6 men rate=1/6, 5 women rate=1/12, combined=1/4, so 4 days.
- Q44 Past Paper · PPSC/FPSC/NTS hard
A contractor undertook to complete a piece of work in 40 days and employed 25 men. After 20 days, he found that only 1/3 of the work was done. How many additional men should he employ to finish the work on time
💡 Explanation:25 men do 1/3 work in 20 days (500 man-days for 1/3); remaining 2/3 needs 1000 man-days in 20 days, requiring 50 men, so 25 more men.
- Q45 hard
A, B and C can do a work in 10, 15 and 30 days respectively. If A is assisted by B and C on every third day, in how many days will the work be completed
💡 Explanation:Every 3-day cycle completes 2/5 of the work; after 6 days 4/5 is done, then 2 more single days of A complete it, total 8 days.