Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 80 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
Page 1 of 1Questions 1–10 of 80
Q1Past Paper · PPSC/FPSC/NTSeasy
Critical activity has
AZero total float✓
BMaximum float always✓
CNegative cost always✓
DInfinite duration✓
💡 Explanation:
Delay on critical activity delays project completion
Q2hard
Free float is delay without affecting
AProject completion always✓
BContract price only✓
CRetirement age✓
DSuccessor earliest start✓
💡 Explanation:
Free float available without impacting next activity
Q3Past Paper · PPSC/FPSC/NTSeasy
Critical Path Method CPM identifies
AShortest path always✓
BOnly resource cost path✓
COnly quality inspection path✓
DLongest path determining project duration✓
💡 Explanation:
Critical path has zero total float and drives completion date
Q4Past Paper · PPSC/FPSC/NTSmedium
Total float of an activity is
AAlways negative✓
BEqual to project cost✓
CTime activity can delay without delaying project✓
DSame as manpower count✓
💡 Explanation:
Float = LS-ES or LF-EF for non-critical activities
Q5Past Paper · PPSC/FPSC/NTSmedium
PERT uses
AThree time estimates for uncertainty✓
BOnly single deterministic time✓
COnly cost estimates✓
DOnly manpower ranks✓
💡 Explanation:
Optimistic most likely pessimistic define beta distribution
Q6Past Paper · PPSC/FPSC/NTShard
Expected time in PERT formula is
AO + M + P✓
B(O + 4M + P) / 6✓
C(O + P) / 2 only✓
DO × P / M✓
💡 Explanation:
Weighted average emphasizes most likely time
Q7Past Paper · PPSC/FPSC/NTSeasy
Bar chart or Gantt chart shows
AActivity duration versus calendar time✓
BOnly soil bore log✓
COnly wind rose✓
DOnly tide table✓
💡 Explanation:
Simple visual schedule for site progress reporting
Q8medium
Resource leveling aims to
AMaximize peak daily labour always✓
BEliminate critical path✓
CIgnore float✓
DSmooth resource demand over time✓
💡 Explanation:
Leveling reduces idle time and overtime peaks
Q9medium
Precedence diagram method uses
AOnly bar colours✓
BNodes for activities and arrows for logic✓
COnly BOQ pages✓
DOnly site photos✓
💡 Explanation:
AON networks show finish-start and other dependencies
Q10hard
Crash cost slope indicates
ASoil friction angle✓
BBitumen penetration✓
CCost to reduce activity duration per unit time✓
DWind speed✓
💡 Explanation:
Crashing trades cost for shorter critical path duration
Q11Past Paper · PPSC/FPSC/NTSeasy
BOQ in construction stands for
ABoard of Quality✓
BBase of Quarry✓
CBalance of Quota✓
DBill of Quantities✓
💡 Explanation:
BOQ itemizes measured work for tender pricing
Q12Past Paper · PPSC/FPSC/NTSeasy
Abstract of cost summarizes
ABOQ amounts with rates and totals✓
BOnly site diary✓
COnly weather log✓
DOnly labour union rules✓
💡 Explanation:
Abstract presents financial summary of estimate
Q13Past Paper · PPSC/FPSC/NTSmedium
Rate analysis determines
AOnly project float✓
BUnit rate for BOQ item✓
COnly seismic zone✓
DOnly wind rose✓
💡 Explanation:
Rate includes materials labour equipment and overheads
Q14Past Paper · PPSC/FPSC/NTSmedium
Lump sum contract pays
AOnly measured quantities always✓
BOnly hourly wages without scope✓
CFixed price for defined scope✓
DOnly material cost without labour✓
💡 Explanation:
Contractor bears quantity risk within scope
Q15Past Paper · PPSC/FPSC/NTSmedium
Unit price contract pays
AAgreed rate times measured quantity✓
BFixed amount regardless of quantity✓
COnly profit without work✓
DOnly mobilization without items✓
💡 Explanation:
Employer pays actual measured work at tender rates
Q16hard
Cost plus contract reimburses
AOnly fixed lump sum always✓
BZero payment until completion without terms✓
CActual cost plus fee✓
DOnly penalty without work✓
💡 Explanation:
Owner pays costs with contractor fee for reimbursable work
Q17Past Paper · PPSC/FPSC/NTSmedium
FIDIC conditions of contract are widely used for
AOnly domestic house painting✓
BOnly railway ticket sales✓
COnly airport retail lease only✓
DInternational civil works including Pakistan projects✓
💡 Explanation:
FIDIC Red/Yellow books common on infrastructure
Q18easy
Mobilization advance helps contractor
AAvoid all work✓
BFund initial site setup and cash flow✓
CSkip safety measures✓
DIgnore schedule✓
💡 Explanation:
Advance recovered from interim payments per contract
Q19medium
Interim payment certificate covers
AOnly final retention release always✓
BOnly bid bond✓
CWork done in billing period✓
DOnly penalty only✓
💡 Explanation:
IPC certifies measured work for partial payment
Q20Past Paper · PPSC/FPSC/NTSmedium
Retention money is withheld to
AEnsure defect liability completion✓
BIncrease contractor profit always✓
CPay unrelated third parties✓
DSkip quality checks✓
💡 Explanation:
Typical 5-10% held until defects period ends
Q21Past Paper · PPSC/FPSC/NTShard
Extension of time EOT granted when
AContractor inefficiency alone✓
BDelay caused by employer risk events✓
CNormal weather always without clause✓
DLow bid error by contractor alone✓
💡 Explanation:
EOT adjusts completion date without penalty if justified
Q22medium
Claim in construction arises from
AOnly congratulation letter✓
BOnly site cleanliness award✓
COnly random audit without issue✓
DDispute over time cost or scope change✓
💡 Explanation:
Claims need records notices and contractual basis
Q23easy
Site organization chart defines
AOnly paint schedule✓
BRoles reporting and communication lines✓
COnly brick colour✓
DOnly carpet pattern✓
💡 Explanation:
Clear hierarchy improves decision making on large sites
Q24medium
Site layout plan locates
ACrane batching plant and material storage✓
BOnly head office city address✓
COnly airport runway✓
DOnly harbour berth✓
💡 Explanation:
Layout minimizes haul and interference on confined sites
Q25easy
Equipment selection depends on
AOnly paint colour✓
BOnly staff uniform✓
CJob size soil conditions and availability✓
DOnly logo design✓
💡 Explanation:
Excavators cranes and plants matched to productivity needs
Q26medium
Productivity of equipment measured by
AOnly fuel colour✓
BOnly operator age✓
COnly serial number✓
DOutput per unit time or cost per cubic metre✓
💡 Explanation:
m³/hour or tonnes/hour benchmarks planning
Q27Past Paper · PPSC/FPSC/NTSeasy
Safety on construction site requires
APPE hazard identification and training✓
BOnly speed without helmets✓
CIgnoring scaffolding rules✓
DUnlimited overtime without rest✓
💡 Explanation:
Pakistan labour laws and best practice mandate site safety
Q28Past Paper · PPSC/FPSC/NTSeasy
Quality control on site includes
AOnly visual guess✓
BOnly oral promise✓
COnly final paint coat✓
DTesting plans inspection and non-conformance reports✓
💡 Explanation:
QC verifies materials and workmanship meet specs
Q29medium
Inspection and test plan ITP schedules
AOnly lunch breaks✓
BHold and witness points for quality checks✓
COnly holiday list✓
DOnly payroll dates✓
💡 Explanation:
ITP aligns contractor QC with engineer surveillance
Q30medium
Progress monitoring uses
AOnly office decoration✓
BOnly stationery stock✓
CPhysical quantity completed versus plan✓
DOnly social media posts✓
💡 Explanation:
S-curves compare planned and actual progress
Q31hard
Earned value management combines
AOnly bitumen grade✓
BOnly wind load✓
COnly tide range✓
DScope schedule and cost performance✓
💡 Explanation:
EVM indices CPI SPI show project health
Q32medium
Risk register documents
AOnly staff birthdays✓
BIdentified risks probability impact and response✓
COnly vehicle numbers✓
DOnly canteen menu✓
💡 Explanation:
Proactive risk management reduces surprises on projects
Q33easy
Scheduling software like Primavera used for
AOnly word processing✓
BOnly photo editing✓
CComplex multi activity project control✓
DOnly email only✓
💡 Explanation:
Software handles logic resources and baseline updates
Q34medium
Work breakdown structure WBS divides
AProject into manageable work packages✓
BOnly payroll into coins✓
COnly soil into colours✓
DOnly rain into seasons only✓
💡 Explanation:
WBS organizes scope for estimating and control
Q35medium
Lead time in procurement affects
AOnly paint drying only✓
BOnly lunch duration✓
CSchedule for long delivery items✓
DOnly meeting applause✓
💡 Explanation:
Steel plants transformers need early order in infrastructure