Q1 easy
Variation order changes
A Only contractor personal plan ✓ B Only unrelated hobby ✓ C Only national holiday list ✓ D Contract scope quantity or design ✓ Show Answer 💡 Explanation: VO adjusts time and cost with mutual agreement
Q2 Past Paper · PPSC/FPSC/NTS easy
Site diary records
A Only fiction stories ✓ B Only stock market ✓ C Daily weather labour plant and progress notes ✓ D Only cricket scores only ✓ Show Answer 💡 Explanation: Contemporaneous records vital for disputes
Q3 Past Paper · PPSC/FPSC/NTS medium
Labour laws in Pakistan construction require
A Safe working hours wages and welfare ✓ B No safety rules ✓ C Child labour legally unrestricted ✓ D Zero record keeping always ✓ Show Answer 💡 Explanation: Compliance with labour regulations mandatory on projects
Q4 easy
Concrete cube testing frequency follows
A Never test any cube ✓ B Project specifications and codes ✓ C Only one cube per project always ✓ D Only when client visits ✓ Show Answer 💡 Explanation: Regular sampling verifies characteristic strength
Q5 medium
Non-conformance report NCR issued when
A Work or material fails specification ✓ B Everything perfect always ✓ C Only pay rise request ✓ D Only holiday approval ✓ Show Answer 💡 Explanation: NCR triggers corrective action before acceptance
Q6 medium
Commissioning follows
A Only excavation start ✓ B Only bid opening ✓ C Only soil survey only ✓ D Mechanical completion and testing ✓ Show Answer 💡 Explanation: Systems tested before handover to owner
Q7 easy
Defects liability period typically lasts
A 50 years always for all items ✓ B One day only ✓ C 6 to 12 months after completion ✓ D Zero days always ✓ Show Answer 💡 Explanation: Contractor remedies defects arising in DLP
Q8 medium
Value engineering seeks
A Gold plating without function ✓ B Required function at lower life cycle cost ✓ C Removing all safety ✓ D Ignoring specifications illegally ✓ Show Answer 💡 Explanation: VE workshops optimize design before construction
Q9 medium
Cash flow projection for contractor shows
A Only historical rainfall ✓ B Only wind direction ✓ C Income and expenditure over project time ✓ D Only soil colour ✓ Show Answer 💡 Explanation: Negative cash flow periods need financing plan
Q10 easy
Subcontractor management includes
A Ignore their work completely ✓ B No contract document ✓ C Unlimited scope creep without record ✓ D Scope coordination safety and payment certification ✓ Show Answer 💡 Explanation: Main contractor responsible for site integration
Q11 hard
Critical chain method focuses on
A Resource constraints and project buffers ✓ B Only optimistic scheduling only ✓ C Only ignoring dependencies ✓ D Only removing all float illegally ✓ Show Answer 💡 Explanation: CCPM adds buffers to protect project completion
Q12 medium
Fast tracking compresses schedule by
A Eliminating all quality checks ✓ B Removing all workers ✓ C Stopping procurement ✓ D Overlapping design and construction phases ✓ Show Answer 💡 Explanation: Parallel activities reduce duration with added risk
Q13 medium
Crashing project schedule means
A Slowing all work deliberately ✓ B Adding resources to shorten critical activities ✓ C Removing equipment ✓ D Ignoring critical path ✓ Show Answer 💡 Explanation: Crash only critical activities cost effectively
Q14 easy
S-curve for progress shows
A Only temperature hourly ✓ B Only wind gust ✓ C Cumulative cost or quantity versus time ✓ D Only tide only ✓ Show Answer 💡 Explanation: Typical sigmoid shape of project expenditure
Q15 easy
Labour productivity affected by
A Skill supervision and material availability ✓ B Only moon phase scientifically proven always ✓ C Only uniform colour ✓ D Only office location city ✓ Show Answer 💡 Explanation: Motivation training and logistics drive output
Q16 medium
Equipment idle time cost reduced by
A Never maintaining machines ✓ B Random breakdown ignoring ✓ C Better scheduling and maintenance ✓ D Using wrong machine size always ✓ Show Answer 💡 Explanation: Match plant capacity to activity demand
Q17 medium
Site investigation before estimate confirms
A Only paint brand ✓ B Only staff names ✓ C Only logo font ✓ D Ground conditions access and constraints ✓ Show Answer 💡 Explanation: Geotech data reduces risk in foundation pricing
Q18 Past Paper · PPSC/FPSC/NTS medium
Contingency in estimate covers
A Known measured BOQ items only ✓ B Unforeseen costs within scope ✓ C Contractor deliberate underbid recovery always ✓ D Profit tax only ✓ Show Answer 💡 Explanation: Contingency percentage reflects project uncertainty
Q19 Past Paper · PPSC/FPSC/NTS medium
Escalation in long projects accounts for
A Inflation in material and labour rates ✓ B Fixed prices forever guaranteed ✓ C Zero price change over 10 years ✓ D Only currency design change ✓ Show Answer 💡 Explanation: Multi-year dams and highways need escalation allowance
Q20 easy
Prequalification of contractors assesses
A Only uniform size ✓ B Financial capacity and experience ✓ C Only vehicle colour ✓ D Only office carpet ✓ Show Answer 💡 Explanation: Employer shortlists capable bidders before tender
Q21 medium
Letter of intent allows
A Early start before formal contract signing ✓ B Unlimited scope without agreement ✓ C No documentation ever ✓ D Automatic price increase unilateral ✓ Show Answer 💡 Explanation: LOI starts mobilization under agreed terms pending contract
Q22 medium
Joint venture on mega projects shares
A Only logo design cost ✓ B Only canteen food ✓ C Only stationery only ✓ D Risk resources and expertise ✓ Show Answer 💡 Explanation: JV combines local and international contractor strengths
Q23 Past Paper · PPSC/FPSC/NTS easy
HSE plan on site covers
A Only profit maximization illegal methods ✓ B Only speeding without PPE ✓ C Health safety and environment procedures ✓ D Only ignoring spills ✓ Show Answer 💡 Explanation: Environmental spills and accidents prevented by HSE
Q24 easy
Look-ahead schedule typically covers
A 2 to 4 weeks detailed work plan ✓ B Entire project 20 years detail daily ✓ C Only yesterday ✓ D Only bid date only ✓ Show Answer 💡 Explanation: Short horizon coordinates trades and resources
Q25 medium
Baseline schedule approved at
A Never approved ever ✓ B After project ends only ✓ C Only during bid preparation ✓ D Project start for performance measurement ✓ Show Answer 💡 Explanation: Baseline frozen for comparing delays and EVM
Q26 medium
Change control procedure ensures
A Random changes without record ✓ B Documented review of scope schedule cost changes ✓ C Verbal only unlimited changes ✓ D Ignore employer approval ✓ Show Answer 💡 Explanation: Formal change prevents uncontrolled growth
Q27 easy
Materials on site stored to
A Leave cement in rain open ✓ B Stack steel in mud pond ✓ C Prevent damage theft and deterioration ✓ D Mix chemicals randomly ✓ Show Answer 💡 Explanation: Proper storage maintains specification compliance
Q28 Past Paper · PPSC/FPSC/NTS medium
Labour camp standards in Pakistan projects should provide
A No sanitation ever ✓ B Adequate shelter sanitation and water ✓ C Overcrowding always ✓ D Zero drinking water ✓ Show Answer 💡 Explanation: Worker welfare affects productivity and legal compliance
Q29 medium
Project close-out includes
A Only starting excavation again ✓ B Only deleting all records ✓ C As-built drawings O&M manuals and final account ✓ D Only abandoning site ✓ Show Answer 💡 Explanation: Handover package enables owner operation
Q30 hard
Dispute resolution clauses may specify
A Adjudication arbitration or courts ✓ B Only physical fight ✓ C Only ignoring issue forever ✓ D Only social media poll ✓ Show Answer 💡 Explanation: Contracts define forum for resolving claims
Q31 medium
KPI for project manager includes
A Only coffee consumption ✓ B Only shoe brand ✓ C Only pen count ✓ D Time cost quality and safety performance ✓ Show Answer 💡 Explanation: Balanced KPIs align with employer objectives
Q32 hard
Lean construction aims to
A Increase idle inventory always ✓ B Reduce waste and improve workflow ✓ C Duplicate work happily ✓ D Ignore pull planning ✓ Show Answer 💡 Explanation: Last planner system improves reliability of commitments
Q33 medium
BIM in project management supports
A Only 2D sketch without data ✓ B Only paper blueprint only forever ✓ C 3D coordination quantity takeoff and clash detection ✓ D Only unrelated gaming ✓ Show Answer 💡 Explanation: Building information modeling reduces rework on complex projects
Q34 Past Paper · PPSC/FPSC/NTS easy
Pakistan Public Procurement Regulatory Authority PPRA governs
A Private birthday parties ✓ B Only cricket rules ✓ C Only airport duty free only ✓ D Government tender procedures ✓ Show Answer 💡 Explanation: PPRA rules apply to public sector construction procurement
Q35 medium
NEPRA or WAPDA projects use
A Formal contract management and supervision ✓ B No supervision ✓ C Only verbal agreement ✓ D Only handshake without BOQ ✓ Show Answer 💡 Explanation: Power sector projects follow rigorous contract administration
Q36 easy
Site measurement for IPC done by
A Only contractor alone always ✓ B Only guess without record ✓ C Engineer or quantity surveyor jointly with contractor ✓ D Only aerial photo without scale ✓ Show Answer 💡 Explanation: Joint measurement reduces payment disputes
Q37 medium
Program evaluation review technique developed for
A Only certain repetitive factory only ✓ B Projects with uncertain activity durations ✓ C Only static sculpture ✓ D Only finished building operation only ✓ Show Answer 💡 Explanation: PERT suited to R&D and one-off complex projects
Q38 easy
Histogram of resources shows
A Only soil gradation curve ✓ B Only wind rose ✓ C Only tide chart ✓ D Resource demand over project duration ✓ Show Answer 💡 Explanation: Histogram highlights peaks needing leveling
Q39 hard
Line of balance used for
A Single unique dam spillway only ✓ B One intersection only always ✓ C Repetitive units like housing blocks ✓ D One painting stroke ✓ Show Answer 💡 Explanation: LOB suits projects with repeated activities
Q40 hard
Time-cost trade-off analysis finds
A Optimum duration for minimum total cost ✓ B Only maximum cost always ✓ C Zero duration magically ✓ D Ignore critical path ✓ Show Answer 💡 Explanation: Total cost = direct + indirect project costs versus duration
Q41 easy
Site instructions document
A Only contractor dreams ✓ B Engineer directions to contractor during work ✓ C Only unrelated novels ✓ D Only old newspapers only ✓ Show Answer 💡 Explanation: Written instructions clarify field changes short of VO
Q42 Past Paper · PPSC/FPSC/NTS easy
Critical activity has
A Zero total float ✓ B Maximum float always ✓ C Negative cost always ✓ D Infinite duration ✓ Show Answer 💡 Explanation: Delay on critical activity delays project completion
Q43 hard
Free float is delay without affecting
A Project completion always ✓ B Contract price only ✓ C Retirement age ✓ D Successor earliest start ✓ Show Answer 💡 Explanation: Free float available without impacting next activity
Q44 Past Paper · PPSC/FPSC/NTS easy
Critical Path Method CPM identifies
A Shortest path always ✓ B Only resource cost path ✓ C Only quality inspection path ✓ D Longest path determining project duration ✓ Show Answer 💡 Explanation: Critical path has zero total float and drives completion date
Q45 Past Paper · PPSC/FPSC/NTS medium
Total float of an activity is
A Always negative ✓ B Equal to project cost ✓ C Time activity can delay without delaying project ✓ D Same as manpower count ✓ Show Answer 💡 Explanation: Float = LS-ES or LF-EF for non-critical activities
Q46 Past Paper · PPSC/FPSC/NTS medium
PERT uses
A Three time estimates for uncertainty ✓ B Only single deterministic time ✓ C Only cost estimates ✓ D Only manpower ranks ✓ Show Answer 💡 Explanation: Optimistic most likely pessimistic define beta distribution
Q47 Past Paper · PPSC/FPSC/NTS hard
Expected time in PERT formula is
A O + M + P ✓ B (O + 4M + P) / 6 ✓ C (O + P) / 2 only ✓ D O × P / M ✓ Show Answer 💡 Explanation: Weighted average emphasizes most likely time
Q48 Past Paper · PPSC/FPSC/NTS easy
Bar chart or Gantt chart shows
A Activity duration versus calendar time ✓ B Only soil bore log ✓ C Only wind rose ✓ D Only tide table ✓ Show Answer 💡 Explanation: Simple visual schedule for site progress reporting
Q49 medium
Resource leveling aims to
A Maximize peak daily labour always ✓ B Eliminate critical path ✓ C Ignore float ✓ D Smooth resource demand over time ✓ Show Answer 💡 Explanation: Leveling reduces idle time and overtime peaks
Q50 medium
Precedence diagram method uses
A Only bar colours ✓ B Nodes for activities and arrows for logic ✓ C Only BOQ pages ✓ D Only site photos ✓ Show Answer 💡 Explanation: AON networks show finish-start and other dependencies
Q51 hard
Crash cost slope indicates
A Soil friction angle ✓ B Bitumen penetration ✓ C Cost to reduce activity duration per unit time ✓ D Wind speed ✓ Show Answer 💡 Explanation: Crashing trades cost for shorter critical path duration
Q52 Past Paper · PPSC/FPSC/NTS easy
BOQ in construction stands for
A Board of Quality ✓ B Base of Quarry ✓ C Balance of Quota ✓ D Bill of Quantities ✓ Show Answer 💡 Explanation: BOQ itemizes measured work for tender pricing
Q53 Past Paper · PPSC/FPSC/NTS easy
Abstract of cost summarizes
A BOQ amounts with rates and totals ✓ B Only site diary ✓ C Only weather log ✓ D Only labour union rules ✓ Show Answer 💡 Explanation: Abstract presents financial summary of estimate
Q54 Past Paper · PPSC/FPSC/NTS medium
Rate analysis determines
A Only project float ✓ B Unit rate for BOQ item ✓ C Only seismic zone ✓ D Only wind rose ✓ Show Answer 💡 Explanation: Rate includes materials labour equipment and overheads
Q55 Past Paper · PPSC/FPSC/NTS medium
Lump sum contract pays
A Only measured quantities always ✓ B Only hourly wages without scope ✓ C Fixed price for defined scope ✓ D Only material cost without labour ✓ Show Answer 💡 Explanation: Contractor bears quantity risk within scope
Q56 Past Paper · PPSC/FPSC/NTS medium
Unit price contract pays
A Agreed rate times measured quantity ✓ B Fixed amount regardless of quantity ✓ C Only profit without work ✓ D Only mobilization without items ✓ Show Answer 💡 Explanation: Employer pays actual measured work at tender rates
Q57 hard
Cost plus contract reimburses
A Only fixed lump sum always ✓ B Zero payment until completion without terms ✓ C Actual cost plus fee ✓ D Only penalty without work ✓ Show Answer 💡 Explanation: Owner pays costs with contractor fee for reimbursable work
Q58 Past Paper · PPSC/FPSC/NTS medium
FIDIC conditions of contract are widely used for
A Only domestic house painting ✓ B Only railway ticket sales ✓ C Only airport retail lease only ✓ D International civil works including Pakistan projects ✓ Show Answer 💡 Explanation: FIDIC Red/Yellow books common on infrastructure
Q59 easy
Mobilization advance helps contractor
A Avoid all work ✓ B Fund initial site setup and cash flow ✓ C Skip safety measures ✓ D Ignore schedule ✓ Show Answer 💡 Explanation: Advance recovered from interim payments per contract
Q60 medium
Interim payment certificate covers
A Only final retention release always ✓ B Only bid bond ✓ C Work done in billing period ✓ D Only penalty only ✓ Show Answer 💡 Explanation: IPC certifies measured work for partial payment
Q61 Past Paper · PPSC/FPSC/NTS medium
Retention money is withheld to
A Ensure defect liability completion ✓ B Increase contractor profit always ✓ C Pay unrelated third parties ✓ D Skip quality checks ✓ Show Answer 💡 Explanation: Typical 5-10% held until defects period ends
Q62 Past Paper · PPSC/FPSC/NTS hard
Extension of time EOT granted when
A Contractor inefficiency alone ✓ B Delay caused by employer risk events ✓ C Normal weather always without clause ✓ D Low bid error by contractor alone ✓ Show Answer 💡 Explanation: EOT adjusts completion date without penalty if justified
Q63 medium
Claim in construction arises from
A Only congratulation letter ✓ B Only site cleanliness award ✓ C Only random audit without issue ✓ D Dispute over time cost or scope change ✓ Show Answer 💡 Explanation: Claims need records notices and contractual basis
Q64 easy
Site organization chart defines
A Only paint schedule ✓ B Roles reporting and communication lines ✓ C Only brick colour ✓ D Only carpet pattern ✓ Show Answer 💡 Explanation: Clear hierarchy improves decision making on large sites
Q65 medium
Site layout plan locates
A Crane batching plant and material storage ✓ B Only head office city address ✓ C Only airport runway ✓ D Only harbour berth ✓ Show Answer 💡 Explanation: Layout minimizes haul and interference on confined sites
Q66 easy
Equipment selection depends on
A Only paint colour ✓ B Only staff uniform ✓ C Job size soil conditions and availability ✓ D Only logo design ✓ Show Answer 💡 Explanation: Excavators cranes and plants matched to productivity needs
Q67 medium
Productivity of equipment measured by
A Only fuel colour ✓ B Only operator age ✓ C Only serial number ✓ D Output per unit time or cost per cubic metre ✓ Show Answer 💡 Explanation: m³/hour or tonnes/hour benchmarks planning
Q68 Past Paper · PPSC/FPSC/NTS easy
Safety on construction site requires
A PPE hazard identification and training ✓ B Only speed without helmets ✓ C Ignoring scaffolding rules ✓ D Unlimited overtime without rest ✓ Show Answer 💡 Explanation: Pakistan labour laws and best practice mandate site safety
Q69 Past Paper · PPSC/FPSC/NTS easy
Quality control on site includes
A Only visual guess ✓ B Only oral promise ✓ C Only final paint coat ✓ D Testing plans inspection and non-conformance reports ✓ Show Answer 💡 Explanation: QC verifies materials and workmanship meet specs
Q70 medium
Inspection and test plan ITP schedules
A Only lunch breaks ✓ B Hold and witness points for quality checks ✓ C Only holiday list ✓ D Only payroll dates ✓ Show Answer 💡 Explanation: ITP aligns contractor QC with engineer surveillance
Q71 medium
Progress monitoring uses
A Only office decoration ✓ B Only stationery stock ✓ C Physical quantity completed versus plan ✓ D Only social media posts ✓ Show Answer 💡 Explanation: S-curves compare planned and actual progress
Q72 hard
Earned value management combines
A Only bitumen grade ✓ B Only wind load ✓ C Only tide range ✓ D Scope schedule and cost performance ✓ Show Answer 💡 Explanation: EVM indices CPI SPI show project health
Q73 medium
Risk register documents
A Only staff birthdays ✓ B Identified risks probability impact and response ✓ C Only vehicle numbers ✓ D Only canteen menu ✓ Show Answer 💡 Explanation: Proactive risk management reduces surprises on projects
Q74 easy
Scheduling software like Primavera used for
A Only word processing ✓ B Only photo editing ✓ C Complex multi activity project control ✓ D Only email only ✓ Show Answer 💡 Explanation: Software handles logic resources and baseline updates
Q75 medium
Work breakdown structure WBS divides
A Project into manageable work packages ✓ B Only payroll into coins ✓ C Only soil into colours ✓ D Only rain into seasons only ✓ Show Answer 💡 Explanation: WBS organizes scope for estimating and control
Q76 medium
Lead time in procurement affects
A Only paint drying only ✓ B Only lunch duration ✓ C Schedule for long delivery items ✓ D Only meeting applause ✓ Show Answer 💡 Explanation: Steel plants transformers need early order in infrastructure
Q77 Past Paper · PPSC/FPSC/NTS easy
Tender documents include
A Only oral quote ✓ B Instructions to bidders drawings specs and BOQ ✓ C Only handshake ✓ D Only social media post ✓ Show Answer 💡 Explanation: Formal tender ensures competitive transparent bidding
Q78 Past Paper · PPSC/FPSC/NTS medium
Bid bond or tender security ensures
A Free unlimited withdrawal without penalty ✓ B Automatic award without evaluation ✓ C No need to submit price ✓ D Serious bidder will accept contract if selected ✓ Show Answer 💡 Explanation: Bond forfeited if bidder withdraws improperly
Q79 medium
Performance bond protects
A Employer if contractor fails to perform ✓ B Contractor from all weather ✓ C Public from free roads always ✓ D Engineer from salary tax only ✓ Show Answer 💡 Explanation: Guarantee typically 5-10% of contract value
Q80 hard
Delay analysis methods include
A Only guessing ✓ B As-planned versus as-built and window analysis ✓ C Only coin toss ✓ D Only horoscope ✓ Show Answer 💡 Explanation: Forensic schedule analysis supports EOT claims