Irrigation Engineering MCQs 2026

79 questions with detailed answers · 28 from past papers · 8 quiz batches available

📚 Civil Engineering Mcqs 📄 28 Past-Paper Qs ✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1 Questions 110 of 79
  1. Q1 Past Paper · PPSC/FPSC/NTS medium

    Kennedy critical velocity V0 depends on

    1. A depth of flow and silt factor
    2. B only canal slope
    3. C only lining thickness
    4. D only gate opening
    💡 Explanation:

    V0 = 0.55 mdy^0.64 in metric form with silt factor m.

  2. Q2 Past Paper · PPSC/FPSC/NTS medium

    Lacey theory defines

    1. A regime perimeter and hydraulic radius for stable alluvial channels
    2. B rigid boundary Manning n only
    3. C pipe Darcy friction
    4. D weir discharge
    💡 Explanation:

    Lacey relates R, V and silt factor for regime channels.

  3. Q3 hard

    Lacey silt factor f is related to average grain size by

    1. A f = d_mm only
    2. B f = 1/d_mm
    3. C f = 1.76 √d_mm
    4. D f = d_mm²
    💡 Explanation:

    Finer sediment reduces permissible velocity and affects regime dimensions.

  4. Q4 Past Paper · PPSC/FPSC/NTS hard

    According to Lacey, wetted perimeter P equals

    1. A 2.67 √Q only always
    2. B 4.75 √Q
    3. C Q/V only
    4. D Manning AR^(2/3)
    💡 Explanation:

    Regime perimeter in metres for discharge Q in cumec.

  5. Q5 Past Paper · PPSC/FPSC/NTS easy

    Freeboard in canals is provided to accommodate

    1. A only boat traffic
    2. B sediment deposition always
    3. C wave action, wind setup and unexpected rises
    4. D zero safety margin
    💡 Explanation:

    Prevents overtopping during surges and operational variations.

  6. Q6 medium

    Canal section is said to be in regime when

    1. A velocity is maximum possible
    2. B depth is always critical
    3. C sediment inflow equals sediment outflow without net scour or fill
    4. D flow is always laminar
    💡 Explanation:

    Equilibrium between erosion and deposition along reach.

  7. Q7 medium

    Side slopes in earthen canals in cutting are typically

    1. A steeper than in filling sections
    2. B always vertical
    3. C always 1:1 in fill and cut
    4. D zero in all cases
    💡 Explanation:

    Cut slopes may be 1:1; fill slopes flatter for stability.

  8. Q8 easy

    Banks in canal design provide

    1. A freeboard storage and structural stability
    2. B only decoration
    3. C zero seepage control alone
    4. D only measurement structures
    💡 Explanation:

    Banks contain flow and allow inspection paths.

  9. Q9 easy

    Bed width in regime canal increases with

    1. A decreases with discharge always
    2. B is independent of Q
    3. C discharge
    4. D equals depth only
    💡 Explanation:

    Larger Q requires wider deeper section per regime relations.

  10. Q10 medium

    Kennedy-Lacey design is most applicable to

    1. A rocky mountain torrents only
    2. B alluvial tracts of Punjab and Sindh type soils
    3. C lined pressure pipelines
    4. D sewer force mains
    💡 Explanation:

    Theories developed for Indo-Gangetic canal systems.

  11. Q11 Past Paper · PPSC/FPSC/NTS easy

    Canal lining primarily reduces

    1. A seepage losses and improves water conveyance efficiency
    2. B canal capacity to zero
    3. C need for outlets
    4. D crop water requirement
    💡 Explanation:

    Lining saves water and stabilizes section against erosion.

  12. Q12 medium

    Cement concrete lining is preferred when

    1. A high durability and low roughness are required
    2. B only temporary diversion needed
    3. C soil is highly erodible without subgrade prep
    4. D no maintenance access exists
    💡 Explanation:

    CC lining has long life with proper expansion joints.

  13. Q13 easy

    Brick lining in canals is

    1. A unsuitable for any canal
    2. B always superior to concrete in all cases
    3. C only for pipes
    4. D economical for moderate heads and good craftsmanship
    💡 Explanation:

    Brick masonry used widely in South Asian minor canals.

  14. Q14 medium

    Plastic membrane lining reduces seepage when protected by

    1. A direct exposure to flow only without cover
    2. B cover layer against puncture and UV damage
    3. C no side protection
    4. D open air only
    💡 Explanation:

    LDPE/PVC membranes need soil or concrete cover.

  15. Q15 medium

    Lining may increase conveyance capacity because

    1. A n always increases
    2. B Manning n decreases for smoother boundary
    3. C slope becomes zero
    4. D depth must decrease always
    💡 Explanation:

    Lower roughness permits higher velocity for same section.

  16. Q16 Past Paper · PPSC/FPSC/NTS easy

    Cross regulator on a canal is provided to

    1. A measure rainfall
    2. B raise water level upstream to divert flow into off-taking channels
    3. C treat sewage
    4. D pump groundwater
    💡 Explanation:

    Head regulator controls ponding for branch canal supplies.

  17. Q17 easy

    Head regulator is located at

    1. A field outlet only
    2. B dam spillway crest
    3. C tube well head
    4. D offtake from parent canal
    💡 Explanation:

    Regulates discharge into branch and maintains diversion pond level.

  18. Q18 medium

    Cross regulator gates are commonly

    1. A vertical lift or radial gates
    2. B only butterfly valves in homes
    3. C only sprinkler heads
    4. D only drip emitters
    💡 Explanation:

    Gates operate to modulate pond level and passing discharge.

  19. Q19 medium

    Tail channel level downstream of regulator affects

    1. A only air temperature
    2. B crop variety only
    3. C soil pH only
    4. D submergence of off-taking structures and discharge
    💡 Explanation:

    Downstream control influences gate operation and diversion.

  20. Q20 Past Paper · PPSC/FPSC/NTS easy

    Canal outlet delivers water from

    1. A reservoir to ocean
    2. B distributary or minor to watercourse or field channel
    3. C sewer to treatment plant
    4. D rain gauge to lab
    💡 Explanation:

    Outlets are farmer turnouts on irrigation network.

  21. Q21 Past Paper · PPSC/FPSC/NTS medium

    Kennedy gauge outlet is

    1. A a modular outlet maintaining constant discharge over varying head
    2. B only siphon tube
    3. C only sprinkler nozzle
    4. D only trickling filter
    💡 Explanation:

    Modular flow independent of downstream level within limits.

  22. Q22 Past Paper · PPSC/FPSC/NTS medium

    Modular outlet means discharge is

    1. A always zero
    2. B always proportional to tail level only
    3. C equal to rainfall
    4. D independent of tail water level within modular range
    💡 Explanation:

    Free flow regime at outlet throat.

  23. Q23 medium

    Non-modular outlet discharge depends on

    1. A upstream only always
    2. B neither level
    3. C wind speed only
    4. D both upstream and downstream water levels
    💡 Explanation:

    Submergence affects discharge coefficient.

  24. Q24 easy

    Orifice type outlet is suited for

    1. A low discharge turnouts from minors
    2. B main river spillway only
    3. C dam foundation
    4. D highway drainage only
    💡 Explanation:

    Simple opening with calibrated discharge-head relation.

  25. Q25 hard

    Pipe outlet with semi-module uses

    1. A rising pipe to break submergence effect partially
    2. B no pipe at all
    3. C only open channel weir at dam
    4. D sewer vent
    💡 Explanation:

    Semi-modular behaviour improves delivery stability.

  26. Q26 medium

    Outlet capacity is fixed considering

    1. A culturable command area and crop water duty
    2. B only canal colour
    3. C bridge width only
    4. D wind direction
    💡 Explanation:

    Design matches authorized discharge to commanded land.

  27. Q27 easy

    Emitter discharge in drip system is typically

    1. A 1000 litres per second
    2. B zero flow always
    3. C equal to canal cumec
    4. D 2–8 litres per hour per emitter
    💡 Explanation:

    Low flow high-frequency application characterizes drip.

  28. Q28 easy

    Filtration in drip irrigation is essential to prevent

    1. A increasing evaporation only
    2. B raising delta always
    3. C canal siltation upstream
    4. D emitter clogging from suspended particles
    💡 Explanation:

    Screen or disc filters maintain micro-pathways.

  29. Q29 medium

    Sprinkler uniformity coefficient measures

    1. A evenness of water application over field
    2. B only wind speed
    3. C only soil pH
    4. D only crop height
    💡 Explanation:

    Christiansen uniformity coefficient used in design.

  30. Q30 medium

    Operating pressure in drip laterals must be within range to

    1. A maximize canal seepage
    2. B maintain design emitter discharge
    3. C stop all flow
    4. D eliminate filtration
    💡 Explanation:

    Pressure compensating emitters widen allowable range.

  31. Q31 medium

    Chemigation through drip lines allows

    1. A only sediment removal from canals
    2. B only canal lining
    3. C fertigation and controlled pesticide application
    4. D only flood routing
    💡 Explanation:

    Fertilizer injected with irrigation water improves efficiency.

  32. Q32 Past Paper · PPSC/FPSC/NTS easy

    Lift irrigation scheme uses pumps when

    1. A source level is below field elevation
    2. B gravity canal suffices
    3. C rainfall meets all demand
    4. D no power available ever
    💡 Explanation:

    Pumping cost is major component of O&M.

  33. Q33 medium

    Pump house in lift irrigation is sited considering

    1. A only aesthetic view
    2. B only downstream sewer
    3. C only highway curve
    4. D suction lift, flood level and power supply
    💡 Explanation:

    NPSH and flood protection govern location.

  34. Q34 medium

    Delivery pipeline in lift scheme is designed for

    1. A pressure head, surge and friction losses
    2. B open channel Manning only
    3. C zero velocity
    4. D atmospheric pressure only
    💡 Explanation:

    Rising mains withstand operating and transient pressures.

  35. Q35 hard

    Stage pumping in lift irrigation is adopted for

    1. A zero head systems
    2. B only siphon flows
    3. C only gravity canals
    4. D high lifts dividing total head among pumps in series
    💡 Explanation:

    Reduces single pump head and improves efficiency.

  36. Q36 easy

    Energy cost in lift irrigation makes

    1. A efficiency irrelevant
    2. B water scheduling and high efficiency methods important
    3. C duty infinite always
    4. D delta zero
    💡 Explanation:

    Power for pumping motivates drip and night irrigation scheduling.

  37. Q37 Past Paper · PPSC/FPSC/NTS easy

    Surface drainage removes

    1. A only salt from soil
    2. B excess water from land surface via channels
    3. C only air pollution
    4. D only groundwater always
    💡 Explanation:

    Open drains lower ponded water after rains or irrigation.

  38. Q38 medium

    Sub-surface drainage uses

    1. A only overhead sprinklers
    2. B only canal lining
    3. C buried perforated pipes or tile drains
    4. D only dam spillway
    💡 Explanation:

    Lowers water table in waterlogged saline areas.

  39. Q39 medium

    Drainage coefficient is defined as

    1. A canal duty only
    2. B depth of water removed in 24 hours from submerged area
    3. C crop delta only
    4. D Manning n
    💡 Explanation:

    mm/day; design basis for drain spacing.

  40. Q40 medium

    Salinity control in irrigated lands often requires

    1. A only increased flooding without drainage
    2. B zero irrigation
    3. C removal of all canals
    4. D leaching and adequate drainage
    💡 Explanation:

    Leaching washes salts; drains remove leachate.

  41. Q41 hard

    Interceptor drain is placed to

    1. A increase water logging
    2. B block irrigation supply
    3. C cut seepage flow from canal or aquifer before field
    4. D raise water table
    💡 Explanation:

    Parallel to canal on downstream side in waterlogged commands.

  42. Q42 easy

    Drainage of rice fields may use

    1. A only pressurized pipe mains
    2. B only trickling filters
    3. C only air lift pumps
    4. D shallow surface drains between bunds
    💡 Explanation:

    Controlled drainage manages water table in paddy.

  43. Q43 Past Paper · PPSC/FPSC/NTS easy

    Water logging is caused primarily by

    1. A only wind erosion
    2. B only canal lining
    3. C only drip irrigation
    4. D high water table and inadequate drainage
    💡 Explanation:

    Shallow water table restricts aeration and crop growth.

  44. Q44 easy

    Canal seepage contributes to water logging by

    1. A lowering water table always
    2. B raising local groundwater table
    3. C removing salts always
    4. D increasing soil strength
    💡 Explanation:

    Unlined canals are major source in commands.

  45. Q45 easy

    Waterlogged soils show symptoms of

    1. A reduced crop yield, salinity and poor aeration
    2. B increased fertility always
    3. C zero evaporation
    4. D higher soil strength for all crops
    💡 Explanation:

    Roots suffer oxygen deficiency.

  46. Q46 medium

    Reclamation of waterlogged land includes

    1. A increasing seepage
    2. B abandoning all irrigation forever
    3. C drainage, land shaping and leaching
    4. D removing topsoil only
    💡 Explanation:

    Integrated surface and subsurface drainage with crop management.

  47. Q47 medium

    Shallow water table within root zone is harmful when it is within

    1. A 50 m always safe
    2. B only during floods never otherwise
    3. C 1–2 m of surface for most crops depending on species
    4. D zero depth required always
    💡 Explanation:

    Crop tolerance to saturation varies.

  48. Q48 medium

    Ponding on surface after irrigation indicates

    1. A perfect soil health always
    2. B excessive drainage always
    3. C low delta only
    4. D poor infiltration or inadequate surface drainage
    💡 Explanation:

    May signal compaction, clay pans or high water table.

  49. Q49 Past Paper · PPSC/FPSC/NTS easy

    Gross command area (GCA) is

    1. A total area served by irrigation scheme including unculturable land
    2. B only cropped area
    3. C only forest reserve always excluded
    4. D only urban area
    💡 Explanation:

    Includes roads, settlements and barren patches within boundary.

  50. Q50 Past Paper · PPSC/FPSC/NTS easy

    Culturable command area (CCA) is

    1. A total dam catchment
    2. B ocean area
    3. C area that can practically be irrigated and cultivated
    4. D only building footprint
    💡 Explanation:

    CCA ≤ GCA; basis for water demand estimates.

  51. Q51 Past Paper · PPSC/FPSC/NTS medium

    Intensity of irrigation is ratio of

    1. A irrigated area to CCA for a given season or year
    2. B canal length to width
    3. C pump power to head only
    4. D rainfall to evaporation only
    💡 Explanation:

    May exceed 100% annually with multiple crops.

  52. Q52 easy

    Increasing irrigation efficiency for same delta will

    1. A decrease duty always
    2. B increase effective duty
    3. C not affect duty
    4. D eliminate base period
    💡 Explanation:

    Less loss means more area served per unit supply.

  53. Q53 medium

    Higher cropping intensity demands

    1. A greater water supply and timely irrigation
    2. B less canal capacity
    3. C zero storage
    4. D no outlets
    💡 Explanation:

    More area-time irrigation increases annual delta demand.

  54. Q54 medium

    Crop water requirement for intensity planning uses

    1. A only highway traffic
    2. B only wind rose
    3. C delta and overlap of crop calendars
    4. D only concrete grade
    💡 Explanation:

    Summed seasonal needs set canal capacity.

  55. Q55 Past Paper · PPSC/FPSC/NTS medium

    Intensity of irrigation for wheat alone of 50% means

    1. A all land grows wheat twice
    2. B half of CCA receives wheat irrigation that season
    3. C no irrigation occurs
    4. D delta is zero
    💡 Explanation:

    Fraction of command under specific crop irrigation.

  56. Q56 medium

    Sustainable cropping intensity is limited by

    1. A only seed colour
    2. B water availability, soil health and drainage capacity
    3. C bridge span
    4. D canal name
    💡 Explanation:

    Over-intensification causes salinity and depletion.

  57. Q57 easy

    Surface irrigation includes

    1. A border, furrow and basin methods
    2. B drip and micro-spray only
    3. C only sprinkler systems
    4. D only sub-surface pipes
    💡 Explanation:

    Flooding methods apply water over soil surface by gravity.

  58. Q58 Past Paper · PPSC/FPSC/NTS easy

    Sprinkler irrigation is most suitable for

    1. A flat clay fields only with high water table
    2. B only rice paddies
    3. C undulating terrain and sandy soils
    4. D only canal-command flat areas
    💡 Explanation:

    Sprinklers provide uniform application where flooding is difficult.

  59. Q59 Past Paper · PPSC/FPSC/NTS easy

    Drip irrigation primarily saves water by

    1. A flooding entire field surface
    2. B increasing runoff
    3. C applying water directly to root zone with minimal evaporation
    4. D raising water table
    💡 Explanation:

    Micro-irrigation has highest application efficiency among methods.

  60. Q60 easy

    Well irrigation is extensively used in

    1. A high mountains without aquifers
    2. B only coastal saline zones
    3. C only deserts without aquifers
    4. D alluvial plains with favourable groundwater
    💡 Explanation:

    Tube wells and dug wells supplement canal supplies in Punjab and Sindh regions.

  61. Q61 Past Paper · PPSC/FPSC/NTS easy

    Canal irrigation systems are classified as

    1. A only drip systems
    2. B only sprinkler grids
    3. C only roof collection
    4. D perennial, non-perennial and inundation canals
    💡 Explanation:

    Perennial canals run year-round from storage; inundation use flood season flow.

  62. Q62 medium

    Lift irrigation is required when

    1. A water table is very high
    2. B land elevation exceeds command of gravity canals
    3. C rainfall exceeds crop need always
    4. D canal is always silt-free
    💡 Explanation:

    Pumps lift water to upland areas beyond contour canal reach.

  63. Q63 Past Paper · PPSC/FPSC/NTS easy

    Duty of water is defined as

    1. A area irrigated per unit discharge over base period
    2. B depth of water only
    3. C canal velocity only
    4. D Manning roughness
    💡 Explanation:

    D = A/Q in hectares per cumec for stated crop and season.

  64. Q64 Past Paper · PPSC/FPSC/NTS easy

    Delta Δ is

    1. A discharge in cumec
    2. B canal bed width
    3. C Lacey perimeter
    4. D total depth of water applied during base period
    💡 Explanation:

    Δ in cm; volume per unit area over crop season.

  65. Q65 Past Paper · PPSC/FPSC/NTS easy

    Base period B is

    1. A time for one irrigation only
    2. B total time between first and last irrigation of crop season
    3. C canal design life
    4. D lining thickness period
    💡 Explanation:

    B in days; links duty and delta through water volume.

  66. Q66 Past Paper · PPSC/FPSC/NTS medium

    Relationship between duty D, delta Δ and base period B is

    1. A D = B/Δ only without constant
    2. B Δ = D/B without conversion
    3. C Δ = 8.64 B/D in metre units with D in ha/cumec and B in days
    4. D B = ΔD/100 only
    💡 Explanation:

    Standard relation from continuity: Q×t = A×depth.

  67. Q67 medium

    Duty is inversely proportional to

    1. A base period always directly
    2. B delta for same base period
    3. C canal slope
    4. D Manning n only
    💡 Explanation:

    Higher water requirement (delta) lowers area served per cumec.

  68. Q68 medium

    Field duty is always

    1. A greater than canal duty
    2. B equal to reservoir duty always
    3. C independent of losses
    4. D less than canal duty due to transit losses
    💡 Explanation:

    Losses in canals and field channels reduce delivered water.

  69. Q69 medium

    Delta for rice in hot climate may reach

    1. A 5–10 cm only always
    2. B zero with sprinkler
    3. C 100–150 cm or more depending on season
    4. D less than wheat always in all regions
    💡 Explanation:

    Puddling and percolation losses increase rice delta.

  70. Q70 Past Paper · PPSC/FPSC/NTS hard

    If duty is 1000 ha/cumec and base period 120 days, delta is approximately

    1. A 50 cm
    2. B 200 cm
    3. C 10 cm
    4. D 103.7 cm
    💡 Explanation:

    Δ = 8.64×120/1000 ≈ 1.037 m = 103.7 cm.

  71. Q71 Past Paper · PPSC/FPSC/NTS medium

    Kennedy theory of canal design assumes

    1. A no sediment in water
    2. B eddy formation along wetted perimeter causes silting-erosion balance
    3. C only concrete lining
    4. D uniform velocity at all depths
    💡 Explanation:

    Critical velocity V0 keeps channel stable in alluvial soils.

  72. Q72 medium

    Culturable area factor accounts for

    1. A Manning n variation
    2. B unculturable land within GCA when estimating CCA
    3. C pipe friction only
    4. D wind speed
    💡 Explanation:

    CCA = factor × GCA typically factor 0.55–0.75.

  73. Q73 easy

    Command area development includes

    1. A only dam construction
    2. B only highway paving
    3. C only air quality monitoring
    4. D field channels, outlets and land leveling
    💡 Explanation:

    On-farm development delivers water to root zone.

  74. Q74 medium

    Rotation of supply in command means

    1. A simultaneous unlimited withdrawal
    2. B zero farmer access
    3. C scheduled water delivery to sections in turn
    4. D random flooding
    💡 Explanation:

    Warabandi is rotational system in Indus basin.

  75. Q75 Past Paper · PPSC/FPSC/NTS easy

    Cropping intensity is expressed as

    1. A delta per crop only
    2. B canal discharge only
    3. C percentage of cropped area to CCA in a year
    4. D rainfall depth only
    💡 Explanation:

    Intensity = (area sown in year / CCA) × 100%.

  76. Q76 easy

    If CCA is 10000 ha and area sown in year is 14000 ha, cropping intensity is

    1. A 100%
    2. B 70%
    3. C 200%
    4. D 140%
    💡 Explanation:

    Multiple cropping raises intensity above 100%.

  77. Q77 easy

    Double cropping means

    1. A only one crop ever
    2. B zero irrigation
    3. C two crops grown on same land within one agricultural year
    4. D only forest cover
    💡 Explanation:

    Common in well-irrigated commands.

  78. Q78 Past Paper · PPSC/FPSC/NTS easy

    Rabi season crops in Pakistan include

    1. A rice and cotton only in kharif exclusively
    2. B only sugarcane in monsoon
    3. C wheat, barley and gram
    4. D only mango orchard
    💡 Explanation:

    Winter season with irrigation from storage.

  79. Q79 Past Paper · PPSC/FPSC/NTS easy

    Kharif season crops include

    1. A wheat only
    2. B gram only
    3. C rice, cotton and maize
    4. D only orchard grapes in winter
    💡 Explanation:

    Monsoon/summer season crops.