Project Planning and Quantity Surveying MCQs 2026

50 questions with detailed answers · 20 from past papers · 5 quiz batches available

📚 Civil Engineering Mcqs 📄 20 Past-Paper Qs ✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1 Questions 110 of 50
  1. Q1 Past Paper · PPSC/FPSC/NTS easy

    Reinforcement quantity taken as

    1. A Length in kilometres only without weight
    2. B Count of workers
    3. C Weight in kg or tonnes from bar schedule
    4. D Volume of concrete ignored always
    💡 Explanation:

    BBS from drawings multiplied by unit weight

  2. Q2 medium

    Earthwork in estimate measured by

    1. A Only truck count without volume
    2. B Bank measure or loose cubic metre per spec
    3. C Only colour of soil
    4. D Only smell of soil
    💡 Explanation:

    Shrinkage swell factors apply between bank and loose

  3. Q3 Past Paper · PPSC/FPSC/NTS medium

    Lead and lift charges in rate analysis cover

    1. A Only profit tax
    2. B Only design fee
    3. C Only insurance of car
    4. D Transport and hoisting of materials
    💡 Explanation:

    Distance vertical lift add to material cost

  4. Q4 easy

    Overhead and profit added to

    1. A Only client furniture
    2. B Only government tax always same as overhead
    3. C Direct cost for contractor unit rate
    4. D Only discount subtracted always
    💡 Explanation:

    Contractor recovers site office margin in rates

  5. Q5 Past Paper · PPSC/FPSC/NTS easy

    Schedule of rates SOR issued by

    1. A Government department for small works
    2. B Random shopkeeper
    3. C Only cricket board
    4. D Only airline
    💡 Explanation:

    PWD irrigation use SOR for petty contracts

  6. Q6 hard

    Percentage rate contract pays

    1. A Fixed lump sum only always
    2. B Percentage over measured cost or defined basis
    3. C Zero documentation
    4. D Only bonus without work
    💡 Explanation:

    Less common now; lump sum and unit price preferred

  7. Q7 Past Paper · PPSC/FPSC/NTS easy

    Quantity surveyor role includes

    1. A Only structural design always
    2. B Only soil testing always
    3. C Only driving train
    4. D Measurement valuation and contract administration
    💡 Explanation:

    QS manages cost from estimate to final account

  8. Q8 easy

    Taking off quantities means

    1. A Removing building parts physically
    2. B Measuring from drawings to calculate work amounts
    3. C Only painting walls
    4. D Only deleting files
    💡 Explanation:

    Manual or software extraction of lengths areas volumes

  9. Q9 medium

    Bill of materials differs from BOQ by listing

    1. A Only staff salaries
    2. B Only land price always
    3. C Materials without full labour plant breakdown
    4. D Only legal fees only
    💡 Explanation:

    BOM for procurement; BOQ for construction contract

  10. Q10 medium

    Revision estimate prepared when

    1. A Design changes significantly from original
    2. B Never changed ever
    3. C Only after project ends
    4. D Only before feasibility
    💡 Explanation:

    Updated cost reflects scope design market changes

  11. Q11 Past Paper · PPSC/FPSC/NTS easy

    Comparative statement of tenders shows

    1. A Only weather data
    2. B Only cricket scores
    3. C Only staff birthdays
    4. D Rates and amounts from each bidder ranked
    💡 Explanation:

    Employer compares responsive bids for award

  12. Q12 Past Paper · PPSC/FPSC/NTS medium

    Lowest bid not always accepted if

    1. A Always must accept lowest legally always without check
    2. B Non-responsive or abnormally low risking performance
    3. C Only highest accepted always
    4. D Random selection
    💡 Explanation:

    PPRA allows rejection with recorded justification

  13. Q13 hard

    Earned value in cost control compares

    1. A Budgeted cost of work performed to actual
    2. B Only invoice date
    3. C Only staff age
    4. D Only vehicle colour
    💡 Explanation:

    EVM integrates scope schedule cost

  14. Q14 medium

    Final account settles

    1. A Only bid bond return without measurement
    2. B Only mobilization without completion
    3. C Only design fee unrelated
    4. D Contract sum adjustments variations claims
    💡 Explanation:

    Agreed final payment closes contract financially

  15. Q15 medium

    Daywork in contract pays

    1. A Lump sum regardless of hours
    2. B Zero payment always
    3. C Labour plant materials at schedule rates plus percentage
    4. D Only profit without work
    💡 Explanation:

    Used for unforeseen minor work by employer direction

  16. Q16 medium

    Provisional sum covers

    1. A Nothing defined ever
    2. B Defined scope with uncertain detail at tender
    3. C Contractor illegal payment
    4. D Only tax evasion
    💡 Explanation:

    Later instructed work valued per contract rules

  17. Q17 hard

    Prime cost sum for

    1. A Free unlimited gift
    2. B Only main contractor profit alone
    3. C Nominated subcontract supply later adjusted
    4. D Only design change without record
    💡 Explanation:

    PC sum with contractor attendance fee

  18. Q18 hard

    Cost plan during design stages RIBA or similar refines

    1. A Estimate at concept schematic detailed stages
    2. B Only after demolition
    3. C Only before idea
    4. D Only never updated
    💡 Explanation:

    Cost planning tracks budget through design development

  19. Q19 medium

    Benchmarking project cost uses

    1. A Only random number
    2. B Only lottery
    3. C Only horoscope
    4. D Similar completed projects indices
    💡 Explanation:

    Historical data adjusts for location time scope

  20. Q20 easy

    S-curve cash flow for owner shows

    1. A Only soil gradation
    2. B Expenditure profile over project duration
    3. C Only wind data
    4. D Only tide chart
    💡 Explanation:

    Front heavy or balanced spending affects financing

  21. Q21 medium

    Benefit-cost ratio greater than one indicates

    1. A Benefits exceed costs in present value terms
    2. B Project always unviable
    3. C Equal ignore decision always
    4. D Only costs matter
    💡 Explanation:

    BCR used in economic appraisal of public works

  22. Q22 hard

    Sensitivity analysis tests

    1. A Only one fixed scenario always
    2. B Only paint colour
    3. C Only staff names
    4. D Effect of variable changes on viability
    💡 Explanation:

    NPV tested against cost overrun demand shortfall

  23. Q23 hard

    Shadow price in economic analysis reflects

    1. A Market price always identical without adjustment
    2. B Zero always
    3. C True social opportunity cost
    4. D Contractor bid only
    💡 Explanation:

    Public sector uses shadow pricing for labour capital forex

  24. Q24 Past Paper · PPSC/FPSC/NTS medium

    Land acquisition cost in feasibility includes

    1. A Compensation resettlement and delays
    2. B Only free land always assumed
    3. C Only interior design
    4. D Only signage
    💡 Explanation:

    ROW cost significant for highways transmission lines

  25. Q25 medium

    Operation and maintenance cost in lifecycle includes

    1. A Only capital cost day one only forever ignored
    2. B Only paint once
    3. C Staff energy repairs over service life
    4. D Only foundation only
    💡 Explanation:

    LCCA compares alternatives over 20-50 years

  26. Q26 easy

    Quantity takeoff software examples

    1. A Only word processor
    2. B Only music player
    3. C Only game engine
    4. D Bluebeam CostX Cubit
    💡 Explanation:

    Digital measurement from PDF CAD models

  27. Q27 medium

    Standard method of measurement avoids

    1. A All ambiguity intentionally
    2. B Ambiguity in item description and unit
    3. C Only verbal contracts
    4. D Only lump sum without scope
    💡 Explanation:

    Consistent rules fair to employer and contractor

  28. Q28 medium

    Cut and fill balance in earthwork estimate aims to

    1. A Maximize haul distance always
    2. B Ignore topography
    3. C Import all soil from abroad always joke item
    4. D Minimize borrow and waste haul
    💡 Explanation:

    Mass diagram optimizes earthwork cost

  29. Q29 hard

    Star rates in contract are

    1. A Illegal always
    2. B Same as tender rates always without process
    3. C New rates agreed for varied work not in BOQ
    4. D Only penalty rates
    💡 Explanation:

    Contract defines procedure to agree star rates

  30. Q30 medium

    Price adjustment formula uses

    1. A Contractor arbitrary invoice always
    2. B Official indices for materials labour fuel
    3. C Only gold price alone always
    4. D Only cricket ranking
    💡 Explanation:

    Linked to inflation indices in long contracts

  31. Q31 Past Paper · PPSC/FPSC/NTS easy

    Work charged to contractor measured by

    1. A Engineer per contract method
    2. B Contractor alone without check always
    3. C Random guess
    4. D Social media vote
    💡 Explanation:

    Engineer certifies quantities for IPC

  32. Q32 Past Paper · PPSC/FPSC/NTS easy

    Detailed estimate prepared from

    1. A Drawings specifications and site measurements
    2. B Only guess without quantity
    3. C Only contractor mood
    4. D Only weather forecast
    💡 Explanation:

    Quantities measured per standard methods for accuracy

  33. Q33 Past Paper · PPSC/FPSC/NTS easy

    Abstract of cost links

    1. A Only site diary
    2. B BOQ quantities rates and amounts
    3. C Only labour names
    4. D Only vehicle log
    💡 Explanation:

    Abstract is financial summary of estimate

  34. Q34 Past Paper · PPSC/FPSC/NTS medium

    Rate analysis for excavation includes

    1. A Only profit without cost
    2. B Only tax without items
    3. C Only contingency only
    4. D Labour equipment and overhead for one unit
    💡 Explanation:

    Unit rate built from material labour plant analysis

  35. Q35 medium

    Depreciation of equipment in rate analysis accounts for

    1. A Wear and tear allocation per hour
    2. B Fuel colour change
    3. C Operator uniform
    4. D Office rent unrelated
    💡 Explanation:

    Ownership cost spread over useful operating hours

  36. Q36 Past Paper · PPSC/FPSC/NTS medium

    BOQ preparation requires

    1. A Random units mixed without rule
    2. B Only lump descriptions without qty
    3. C Standard method of measurement for items
    4. D Only photographs
    💡 Explanation:

    PCEM or CESMM style rules ensure comparable tenders

  37. Q37 Past Paper · PPSC/FPSC/NTS easy

    Tender documents package includes

    1. A Only oral quote
    2. B Instructions drawings specs BOQ and conditions
    3. C Only one sketch
    4. D Only email hello
    💡 Explanation:

    Complete package defines scope for bidding

  38. Q38 Past Paper · PPSC/FPSC/NTS medium

    Contingency allowance covers

    1. A Unforeseen work within project scope
    2. B Known BOQ items priced twice
    3. C Contractor profit guarantee
    4. D Tax bribe illegal item
    💡 Explanation:

    Typically 5-15% depending on design completeness

  39. Q39 Past Paper · PPSC/FPSC/NTS medium

    Escalation clause in contract adjusts

    1. A Fixed price forever without change ever
    2. B Only contractor hobby costs
    3. C Only paint colour change
    4. D Rates for inflation over long execution period
    💡 Explanation:

    Multi-year projects need price adjustment mechanism

  40. Q40 easy

    Project life cycle phases include

    1. A Only excavation always
    2. B Initiation planning execution closure
    3. C Only painting always
    4. D Only demolition only
    💡 Explanation:

    Standard PM lifecycle for infrastructure

  41. Q41 Past Paper · PPSC/FPSC/NTS easy

    Feasibility study determines

    1. A Only paint schedule
    2. B Only staff lunch menu
    3. C Technical economic and financial viability
    4. D Only logo design only
    💡 Explanation:

    Go/no-go decision before detailed design

  42. Q42 Past Paper · PPSC/FPSC/NTS medium

    NPV positive means

    1. A Always loss
    2. B Break even only always
    3. C Ignore time value of money
    4. D Project returns exceed discount rate
    💡 Explanation:

    Net present value sums discounted cash flows

  43. Q43 Past Paper · PPSC/FPSC/NTS medium

    IRR is discount rate when

    1. A Cost equals zero always
    2. B NPV equals zero
    3. C Benefit undefined
    4. D Tax equals zero only
    💡 Explanation:

    Internal rate of return compared to hurdle rate

  44. Q44 easy

    Payback period measures

    1. A Total project life always
    2. B Only design phase
    3. C Time to recover initial investment
    4. D Only maintenance only
    💡 Explanation:

    Simple metric ignoring cash flows after payback

  45. Q45 Past Paper · PPSC/FPSC/NTS medium

    Cost-benefit analysis compares

    1. A Present value of benefits and costs
    2. B Only contractor mood
    3. C Only soil colour
    4. D Only wind rose
    💡 Explanation:

    Public projects use CBA for economic justification

  46. Q46 medium

    Measurement rules for concrete may be

    1. A By guess bags only
    2. B By cubic metre in place net of openings
    3. C By surface paint area only
    4. D By weight of rebar only without concrete
    💡 Explanation:

    Standard rules avoid disputes in payment

  47. Q47 Past Paper · PPSC/FPSC/NTS easy

    Plinth area estimate used for

    1. A Final contractor payment without detail
    2. B Harbour dredging quantity
    3. C Railway signalling
    4. D Rough cost of buildings early stage
    💡 Explanation:

    Quick cost per square foot based on plinth area

  48. Q48 medium

    Centre line method suits

    1. A Regular symmetric walls and trenches
    2. B Irregular scattered footings only always
    3. C Only paint work
    4. D Only landscaping only
    💡 Explanation:

    Mean length times breadth height for walls

  49. Q49 medium

    Long wall short wall method used in

    1. A Circular tank only always
    2. B Only highway ESAL
    3. C Building with varying wall lengths
    4. D Only airport runway
    💡 Explanation:

    Long walls and short walls measured separately

  50. Q50 easy

    Unit of measurement for brick masonry commonly

    1. A Cubic metre or per square metre wall
    2. B Kilometre length only
    3. C Litre volume only for all
    4. D Tonnes always only
    💡 Explanation:

    Spec defines whether volume or area basis