Project Planning and Quantity Surveying MCQs 2026
50 questions with detailed answers · 20 from past papers · 5 quiz batches available
Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 50 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
- Q1 Past Paper · PPSC/FPSC/NTS easy
Reinforcement quantity taken as
💡 Explanation:BBS from drawings multiplied by unit weight
- Q2 medium
Earthwork in estimate measured by
💡 Explanation:Shrinkage swell factors apply between bank and loose
- Q3 Past Paper · PPSC/FPSC/NTS medium
Lead and lift charges in rate analysis cover
💡 Explanation:Distance vertical lift add to material cost
- Q4 easy
Overhead and profit added to
💡 Explanation:Contractor recovers site office margin in rates
- Q5 Past Paper · PPSC/FPSC/NTS easy
Schedule of rates SOR issued by
💡 Explanation:PWD irrigation use SOR for petty contracts
- Q6 hard
Percentage rate contract pays
💡 Explanation:Less common now; lump sum and unit price preferred
- Q7 Past Paper · PPSC/FPSC/NTS easy
Quantity surveyor role includes
💡 Explanation:QS manages cost from estimate to final account
- Q8 easy
Taking off quantities means
💡 Explanation:Manual or software extraction of lengths areas volumes
- Q9 medium
Bill of materials differs from BOQ by listing
💡 Explanation:BOM for procurement; BOQ for construction contract
- Q10 medium
Revision estimate prepared when
💡 Explanation:Updated cost reflects scope design market changes
- Q11 Past Paper · PPSC/FPSC/NTS easy
Comparative statement of tenders shows
💡 Explanation:Employer compares responsive bids for award
- Q12 Past Paper · PPSC/FPSC/NTS medium
Lowest bid not always accepted if
💡 Explanation:PPRA allows rejection with recorded justification
- Q13 hard
Earned value in cost control compares
💡 Explanation:EVM integrates scope schedule cost
- Q14 medium
Final account settles
💡 Explanation:Agreed final payment closes contract financially
- Q15 medium
Daywork in contract pays
💡 Explanation:Used for unforeseen minor work by employer direction
- Q16 medium
Provisional sum covers
💡 Explanation:Later instructed work valued per contract rules
- Q17 hard
Prime cost sum for
💡 Explanation:PC sum with contractor attendance fee
- Q18 hard
Cost plan during design stages RIBA or similar refines
💡 Explanation:Cost planning tracks budget through design development
- Q19 medium
Benchmarking project cost uses
💡 Explanation:Historical data adjusts for location time scope
- Q20 easy
S-curve cash flow for owner shows
💡 Explanation:Front heavy or balanced spending affects financing
- Q21 medium
Benefit-cost ratio greater than one indicates
💡 Explanation:BCR used in economic appraisal of public works
- Q22 hard
Sensitivity analysis tests
💡 Explanation:NPV tested against cost overrun demand shortfall
- Q23 hard
Shadow price in economic analysis reflects
💡 Explanation:Public sector uses shadow pricing for labour capital forex
- Q24 Past Paper · PPSC/FPSC/NTS medium
Land acquisition cost in feasibility includes
💡 Explanation:ROW cost significant for highways transmission lines
- Q25 medium
Operation and maintenance cost in lifecycle includes
💡 Explanation:LCCA compares alternatives over 20-50 years
- Q26 easy
Quantity takeoff software examples
💡 Explanation:Digital measurement from PDF CAD models
- Q27 medium
Standard method of measurement avoids
💡 Explanation:Consistent rules fair to employer and contractor
- Q28 medium
Cut and fill balance in earthwork estimate aims to
💡 Explanation:Mass diagram optimizes earthwork cost
- Q29 hard
Star rates in contract are
💡 Explanation:Contract defines procedure to agree star rates
- Q30 medium
Price adjustment formula uses
💡 Explanation:Linked to inflation indices in long contracts
- Q31 Past Paper · PPSC/FPSC/NTS easy
Work charged to contractor measured by
💡 Explanation:Engineer certifies quantities for IPC
- Q32 Past Paper · PPSC/FPSC/NTS easy
Detailed estimate prepared from
💡 Explanation:Quantities measured per standard methods for accuracy
- Q33 Past Paper · PPSC/FPSC/NTS easy
Abstract of cost links
💡 Explanation:Abstract is financial summary of estimate
- Q34 Past Paper · PPSC/FPSC/NTS medium
Rate analysis for excavation includes
💡 Explanation:Unit rate built from material labour plant analysis
- Q35 medium
Depreciation of equipment in rate analysis accounts for
💡 Explanation:Ownership cost spread over useful operating hours
- Q36 Past Paper · PPSC/FPSC/NTS medium
BOQ preparation requires
💡 Explanation:PCEM or CESMM style rules ensure comparable tenders
- Q37 Past Paper · PPSC/FPSC/NTS easy
Tender documents package includes
💡 Explanation:Complete package defines scope for bidding
- Q38 Past Paper · PPSC/FPSC/NTS medium
Contingency allowance covers
💡 Explanation:Typically 5-15% depending on design completeness
- Q39 Past Paper · PPSC/FPSC/NTS medium
Escalation clause in contract adjusts
💡 Explanation:Multi-year projects need price adjustment mechanism
- Q40 easy
Project life cycle phases include
💡 Explanation:Standard PM lifecycle for infrastructure
- Q41 Past Paper · PPSC/FPSC/NTS easy
Feasibility study determines
💡 Explanation:Go/no-go decision before detailed design
- Q42 Past Paper · PPSC/FPSC/NTS medium
NPV positive means
💡 Explanation:Net present value sums discounted cash flows
- Q43 Past Paper · PPSC/FPSC/NTS medium
IRR is discount rate when
💡 Explanation:Internal rate of return compared to hurdle rate
- Q44 easy
Payback period measures
💡 Explanation:Simple metric ignoring cash flows after payback
- Q45 Past Paper · PPSC/FPSC/NTS medium
Cost-benefit analysis compares
💡 Explanation:Public projects use CBA for economic justification
- Q46 medium
Measurement rules for concrete may be
💡 Explanation:Standard rules avoid disputes in payment
- Q47 Past Paper · PPSC/FPSC/NTS easy
Plinth area estimate used for
💡 Explanation:Quick cost per square foot based on plinth area
- Q48 medium
Centre line method suits
💡 Explanation:Mean length times breadth height for walls
- Q49 medium
Long wall short wall method used in
💡 Explanation:Long walls and short walls measured separately
- Q50 easy
Unit of measurement for brick masonry commonly
💡 Explanation:Spec defines whether volume or area basis