Capital Budgeting MCQs 2026

75 questions with detailed answers · 29 from past papers · 8 quiz batches available

📚 Finance Mcqs 📄 29 Past-Paper Qs ✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1 Questions 110 of 75
  1. Q1 Past Paper · PPSC/FPSC/NTS easy

    Net Present Value (NPV) criterion accepts a standalone project when

    1. A IRR equals zero only
    2. B payback exceeds five years
    3. C NPV is greater than zero
    4. D accounting profit is negative
    💡 Explanation:

    Positive NPV adds shareholder value.

  2. Q2 Past Paper · PPSC/FPSC/NTS easy

    Internal Rate of Return (IRR) is the discount rate that makes

    1. A payback period equal to project life
    2. B accounting ROI maximum
    3. C PI equal to two
    4. D NPV equal to zero
    💡 Explanation:

    IRR solves NPV=0 for r.

  3. Q3 medium

    Profitability Index equals

    1. A present value of inflows divided by initial investment
    2. B NPV divided by salvage value
    3. C IRR times payback
    4. D book profit divided by sales
    💡 Explanation:

    PI = PV benefits / PV costs.

  4. Q4 Past Paper · PPSC/FPSC/NTS medium

    Payback period ignores

    1. A initial investment amount
    2. B operating cash inflows
    3. C project life entirely
    4. D cash flows beyond the payback cutoff and time value of money
    💡 Explanation:

    Payback is a liquidity, not value, measure.

  5. Q5 medium

    Discounted payback period improves on simple payback by

    1. A ignoring terminal salvage
    2. B using accounting income
    3. C discounting cash flows before accumulation
    4. D excluding initial outlay
    💡 Explanation:

    Time value incorporated in discounted payback.

  6. Q6 Past Paper · PPSC/FPSC/NTS hard

    Mutually exclusive projects should be ranked by

    1. A IRR always without exception
    2. B NPV when scales differ
    3. C payback only
    4. D accounting profit margin
    💡 Explanation:

    IRR may conflict with NPV for mutually exclusive projects.

  7. Q7 medium

    Capital rationing exists when

    1. A funds available for investment are limited
    2. B all positive NPV projects can be funded
    3. C WACC is zero
    4. D depreciation is accelerated
    💡 Explanation:

    Firm cannot accept all value-adding projects.

  8. Q8 Past Paper · PPSC/FPSC/NTS medium

    Sunk costs in capital budgeting are

    1. A always subtracted from NPV
    2. B irrelevant to project accept-reject decisions
    3. C the primary cash flow input
    4. D equal to opportunity costs
    💡 Explanation:

    Only incremental future cash flows matter.

  9. Q9 medium

    Opportunity cost of using owned land for a project is

    1. A the rent or value foregone from best alternative use
    2. B zero because land is already owned
    3. C historical purchase price only
    4. D annual depreciation only
    💡 Explanation:

    Opportunity cost is an economic concept.

  10. Q10 Past Paper · PPSC/FPSC/NTS hard

    Terminal year cash flow in NPV analysis typically includes

    1. A only depreciation tax shield
    2. B operating cash flow plus after-tax salvage minus recovery adjustments
    3. C only working capital build
    4. D only interest expense
    💡 Explanation:

    Incremental terminal flows affect NPV.

  11. Q11 medium

    Replacement decision analysis uses

    1. A incremental cash flows of new versus old asset
    2. B full book value of old asset as sunk benefit
    3. C only purchase price of new machine
    4. D historical cost of both assets
    💡 Explanation:

    Compare incremental inflows and outflows.

  12. Q12 Past Paper · PPSC/FPSC/NTS medium

    Scenario analysis in capital budgeting varies

    1. A key inputs like sales growth and cost assumptions
    2. B only the color of equipment
    3. C only audit opinions
    4. D only dividend dates
    💡 Explanation:

    Tests sensitivity to plausible scenarios.

  13. Q13 hard

    Real options in capital budgeting include

    1. A mandatory annual audit
    2. B fixed depreciation schedule only
    3. C statutory tax filing
    4. D option to expand, abandon, or delay a project
    💡 Explanation:

    Flexibility has option value.

  14. Q14 Past Paper · PPSC/FPSC/NTS hard

    Equivalent Annual Annuity approach helps compare projects with

    1. A identical cash flows only
    2. B zero salvage always
    3. C unequal lives
    4. D negative NPV only
    💡 Explanation:

    EAA converts NPV to annuity equivalent.

  15. Q15 hard

    Inflation in cash flow forecasting requires

    1. A mixing real cash flows with nominal discount rate
    2. B ignoring wage growth
    3. C consistent nominal or real rates and cash flows
    4. D using book values only
    💡 Explanation:

    Real/nominal consistency is essential.

  16. Q16 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 20: initial cost Rs 333,000, annual inflow Rs 64,200 for 7 years, discount rate 12%. NPV is approximately

    1. A Rs 292,993
    2. B Rs -40,007
    3. C Rs -333,000
    4. D Rs -80,007
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  17. Q17 medium

    Capital budgeting analysis 21 for ERP system project must correctly treat depreciation tax shield by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D adding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 21: depreciation tax shield for ERP system.

  18. Q18 hard

    NPV exercise 22: initial cost Rs 332,000, annual inflow Rs 61,800 for 4 years, discount rate 14%. NPV is approximately

    1. A Rs 180,067
    2. B Rs -151,933
    3. C Rs -332,000
    4. D Rs -191,933
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  19. Q19 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 23 for waste treatment facility project must correctly treat depreciation tax shield by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C adding depreciation tax shield to operating cash flows
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 23: depreciation tax shield for waste treatment facility.

  20. Q20 hard

    NPV exercise 24: initial cost Rs 366,000, annual inflow Rs 69,400 for 6 years, discount rate 16%. NPV is approximately

    1. A Rs 255,721
    2. B Rs -110,279
    3. C Rs -366,000
    4. D Rs -150,279
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  21. Q21 hard

    Capital budgeting analysis 25 for solar power plant project must correctly treat opportunity cost of land by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C charging foregone rent or best alternative use value
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 25: opportunity cost of land for solar power plant.

  22. Q22 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 26: initial cost Rs 400,000, annual inflow Rs 67,000 for 3 years, discount rate 10%. NPV is approximately

    1. A Rs 166,619
    2. B Rs -233,381
    3. C Rs -400,000
    4. D Rs -273,381
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  23. Q23 medium

    Capital budgeting analysis 27 for warehouse automation project must correctly treat opportunity cost of land by

    1. A charging foregone rent or best alternative use value
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 27: opportunity cost of land for warehouse automation.

  24. Q24 hard

    NPV exercise 28: initial cost Rs 434,000, annual inflow Rs 74,600 for 5 years, discount rate 12%. NPV is approximately

    1. A Rs 268,916
    2. B Rs -165,084
    3. C Rs -434,000
    4. D Rs -205,084
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  25. Q25 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 29 for ERP system project must correctly treat opportunity cost of land by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D charging foregone rent or best alternative use value
    💡 Explanation:

    Project 29: opportunity cost of land for ERP system.

  26. Q26 hard

    NPV exercise 30: initial cost Rs 433,000, annual inflow Rs 82,200 for 7 years, discount rate 14%. NPV is approximately

    1. A Rs 352,499
    2. B Rs -433,000
    3. C Rs -80,501
    4. D Rs -120,501
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  27. Q27 hard

    Capital budgeting analysis 31 for waste treatment facility project must correctly treat opportunity cost of land by

    1. A capitalizing all historical costs into initial outlay
    2. B charging foregone rent or best alternative use value
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 31: opportunity cost of land for waste treatment facility.

  28. Q28 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 32: initial cost Rs 467,000, annual inflow Rs 79,800 for 4 years, discount rate 16%. NPV is approximately

    1. A Rs -243,705
    2. B Rs 223,295
    3. C Rs -467,000
    4. D Rs -283,705
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  29. Q29 medium

    Capital budgeting analysis 33 for solar power plant project must correctly treat sunk R&D costs treatment by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C excluding prior R&D as irrelevant to accept-reject decision
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 33: sunk R&D costs treatment for solar power plant.

  30. Q30 hard

    NPV exercise 34: initial cost Rs 501,000, annual inflow Rs 87,400 for 6 years, discount rate 10%. NPV is approximately

    1. A Rs 380,650
    2. B Rs -501,000
    3. C Rs -120,350
    4. D Rs -160,350
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  31. Q31 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 35 for warehouse automation project must correctly treat sunk R&D costs treatment by

    1. A excluding prior R&D as irrelevant to accept-reject decision
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 35: sunk R&D costs treatment for warehouse automation.

  32. Q32 hard

    NPV exercise 36: initial cost Rs 500,000, annual inflow Rs 85,000 for 3 years, discount rate 12%. NPV is approximately

    1. A Rs 204,156
    2. B Rs -500,000
    3. C Rs -295,844
    4. D Rs -335,844
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  33. Q33 Past Paper · PPSC/FPSC/NTS hard

    Capital budgeting analysis 37 for ERP system project must correctly treat sunk R&D costs treatment by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D excluding prior R&D as irrelevant to accept-reject decision
    💡 Explanation:

    Project 37: sunk R&D costs treatment for ERP system.

  34. Q34 hard

    NPV exercise 38: initial cost Rs 534,000, annual inflow Rs 92,600 for 5 years, discount rate 14%. NPV is approximately

    1. A Rs -216,097
    2. B Rs 317,903
    3. C Rs -534,000
    4. D Rs -256,097
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  35. Q35 medium

    Capital budgeting analysis 39 for waste treatment facility project must correctly treat sunk R&D costs treatment by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D excluding prior R&D as irrelevant to accept-reject decision
    💡 Explanation:

    Project 39: sunk R&D costs treatment for waste treatment facility.

  36. Q36 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 40: initial cost Rs 568,000, annual inflow Rs 100,200 for 7 years, discount rate 16%. NPV is approximately

    1. A Rs 404,664
    2. B Rs -568,000
    3. C Rs -163,336
    4. D Rs -203,336
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  37. Q37 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 60: initial cost Rs 803,000, annual inflow Rs 136,200 for 7 years, discount rate 12%. NPV is approximately

    1. A Rs -181,416
    2. B Rs 621,584
    3. C Rs -803,000
    4. D Rs -221,416
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  38. Q38 medium

    Capital budgeting analysis 41 for solar power plant project must correctly treat inflation in cash flows by

    1. A capitalizing all historical costs into initial outlay
    2. B using consistent nominal cash flows and nominal discount rate
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 41: inflation in cash flows for solar power plant.

  39. Q39 hard

    Capital budgeting analysis 1 for solar power plant project must correctly treat salvage value estimation by

    1. A including after-tax salvage in terminal year cash flow
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 1: salvage value estimation for solar power plant.

  40. Q40 hard

    NPV exercise 2: initial cost Rs 97,000, annual inflow Rs 25,800 for 4 years, discount rate 10%. NPV is approximately

    1. A Rs 81,783
    2. B Rs -97,000
    3. C Rs -55,217
    4. D Rs -15,217
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  41. Q41 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 3 for warehouse automation project must correctly treat salvage value estimation by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C including after-tax salvage in terminal year cash flow
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 3: salvage value estimation for warehouse automation.

  42. Q42 hard

    NPV exercise 4: initial cost Rs 131,000, annual inflow Rs 33,400 for 6 years, discount rate 12%. NPV is approximately

    1. A Rs 137,321
    2. B Rs -131,000
    3. C Rs -33,679
    4. D Rs 6,321
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  43. Q43 medium

    Capital budgeting analysis 5 for ERP system project must correctly treat salvage value estimation by

    1. A including after-tax salvage in terminal year cash flow
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 5: salvage value estimation for ERP system.

  44. Q44 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 6: initial cost Rs 165,000, annual inflow Rs 31,000 for 3 years, discount rate 14%. NPV is approximately

    1. A Rs -93,029
    2. B Rs 71,971
    3. C Rs -165,000
    4. D Rs -133,029
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  45. Q45 hard

    Capital budgeting analysis 7 for waste treatment facility project must correctly treat salvage value estimation by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C including after-tax salvage in terminal year cash flow
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 7: salvage value estimation for waste treatment facility.

  46. Q46 hard

    NPV exercise 8: initial cost Rs 164,000, annual inflow Rs 38,600 for 5 years, discount rate 16%. NPV is approximately

    1. A Rs -37,612
    2. B Rs 126,388
    3. C Rs -164,000
    4. D Rs -77,612
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  47. Q47 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 9 for solar power plant project must correctly treat working capital recovery in terminal year by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C adding back net working capital release at project end
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 9: working capital recovery in terminal year for solar power plant.

  48. Q48 hard

    NPV exercise 10: initial cost Rs 198,000, annual inflow Rs 46,200 for 7 years, discount rate 10%. NPV is approximately

    1. A Rs 224,921
    2. B Rs 26,921
    3. C Rs -198,000
    4. D Rs -13,079
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  49. Q49 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 11 for warehouse automation project must correctly treat working capital recovery in terminal year by

    1. A capitalizing all historical costs into initial outlay
    2. B adding back net working capital release at project end
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 11: working capital recovery in terminal year for warehouse automation.

  50. Q50 hard

    NPV exercise 12: initial cost Rs 232,000, annual inflow Rs 43,800 for 4 years, discount rate 12%. NPV is approximately

    1. A Rs -98,964
    2. B Rs 133,036
    3. C Rs -232,000
    4. D Rs -138,964
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  51. Q51 hard

    Capital budgeting analysis 13 for ERP system project must correctly treat working capital recovery in terminal year by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D adding back net working capital release at project end
    💡 Explanation:

    Project 13: working capital recovery in terminal year for ERP system.

  52. Q52 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 14: initial cost Rs 266,000, annual inflow Rs 51,400 for 6 years, discount rate 14%. NPV is approximately

    1. A Rs 199,878
    2. B Rs -266,000
    3. C Rs -106,122
    4. D Rs -66,122
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  53. Q53 medium

    Capital budgeting analysis 15 for waste treatment facility project must correctly treat working capital recovery in terminal year by

    1. A capitalizing all historical costs into initial outlay
    2. B adding back net working capital release at project end
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 15: working capital recovery in terminal year for waste treatment facility.

  54. Q54 hard

    NPV exercise 16: initial cost Rs 265,000, annual inflow Rs 49,000 for 3 years, discount rate 16%. NPV is approximately

    1. A Rs -154,951
    2. B Rs 110,049
    3. C Rs -265,000
    4. D Rs -194,951
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  55. Q55 Past Paper · PPSC/FPSC/NTS medium

    Capital budgeting analysis 17 for solar power plant project must correctly treat depreciation tax shield by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D adding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 17: depreciation tax shield for solar power plant.

  56. Q56 hard

    NPV exercise 18: initial cost Rs 299,000, annual inflow Rs 56,600 for 5 years, discount rate 10%. NPV is approximately

    1. A Rs 214,559
    2. B Rs -84,441
    3. C Rs -299,000
    4. D Rs -124,441
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  57. Q57 hard

    Capital budgeting analysis 19 for warehouse automation project must correctly treat depreciation tax shield by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C ignoring terminal year cash flows entirely
    4. D adding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 19: depreciation tax shield for warehouse automation.

  58. Q58 hard

    NPV exercise 42: initial cost Rs 602,000, annual inflow Rs 97,800 for 4 years, discount rate 10%. NPV is approximately

    1. A Rs -291,987
    2. B Rs 310,013
    3. C Rs -602,000
    4. D Rs -331,987
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  59. Q59 Past Paper · PPSC/FPSC/NTS hard

    Capital budgeting analysis 43 for warehouse automation project must correctly treat inflation in cash flows by

    1. A capitalizing all historical costs into initial outlay
    2. B using consistent nominal cash flows and nominal discount rate
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 43: inflation in cash flows for warehouse automation.

  60. Q60 hard

    NPV exercise 44: initial cost Rs 601,000, annual inflow Rs 105,400 for 6 years, discount rate 12%. NPV is approximately

    1. A Rs 433,342
    2. B Rs -601,000
    3. C Rs -167,658
    4. D Rs -207,658
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  61. Q61 medium

    Capital budgeting analysis 45 for ERP system project must correctly treat inflation in cash flows by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C using consistent nominal cash flows and nominal discount rate
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 45: inflation in cash flows for ERP system.

  62. Q62 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 46: initial cost Rs 635,000, annual inflow Rs 103,000 for 3 years, discount rate 14%. NPV is approximately

    1. A Rs 239,128
    2. B Rs -635,000
    3. C Rs -435,872
    4. D Rs -395,872
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  63. Q63 medium

    Capital budgeting analysis 47 for waste treatment facility project must correctly treat inflation in cash flows by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C using consistent nominal cash flows and nominal discount rate
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 47: inflation in cash flows for waste treatment facility.

  64. Q64 hard

    NPV exercise 48: initial cost Rs 669,000, annual inflow Rs 110,600 for 5 years, discount rate 16%. NPV is approximately

    1. A Rs 362,137
    2. B Rs -669,000
    3. C Rs -346,863
    4. D Rs -306,863
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  65. Q65 Past Paper · PPSC/FPSC/NTS hard

    Capital budgeting analysis 49 for solar power plant project must correctly treat risk-adjusted discount rate by

    1. A using hurdle rate reflecting project-specific business risk
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 49: risk-adjusted discount rate for solar power plant.

  66. Q66 hard

    NPV exercise 50: initial cost Rs 668,000, annual inflow Rs 118,200 for 7 years, discount rate 10%. NPV is approximately

    1. A Rs 575,447
    2. B Rs -92,553
    3. C Rs -668,000
    4. D Rs -132,553
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  67. Q67 medium

    Capital budgeting analysis 51 for warehouse automation project must correctly treat risk-adjusted discount rate by

    1. A capitalizing all historical costs into initial outlay
    2. B using hurdle rate reflecting project-specific business risk
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 51: risk-adjusted discount rate for warehouse automation.

  68. Q68 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 52: initial cost Rs 702,000, annual inflow Rs 115,800 for 4 years, discount rate 12%. NPV is approximately

    1. A Rs 351,725
    2. B Rs -702,000
    3. C Rs -390,275
    4. D Rs -350,275
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  69. Q69 medium

    Capital budgeting analysis 53 for ERP system project must correctly treat risk-adjusted discount rate by

    1. A using hurdle rate reflecting project-specific business risk
    2. B capitalizing all historical costs into initial outlay
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 53: risk-adjusted discount rate for ERP system.

  70. Q70 hard

    NPV exercise 54: initial cost Rs 736,000, annual inflow Rs 123,400 for 6 years, discount rate 14%. NPV is approximately

    1. A Rs 479,862
    2. B Rs -736,000
    3. C Rs -296,138
    4. D Rs -256,138
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  71. Q71 Past Paper · PPSC/FPSC/NTS hard

    Capital budgeting analysis 55 for waste treatment facility project must correctly treat risk-adjusted discount rate by

    1. A capitalizing all historical costs into initial outlay
    2. B using accounting net income without adjustment
    3. C using hurdle rate reflecting project-specific business risk
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 55: risk-adjusted discount rate for waste treatment facility.

  72. Q72 hard

    NPV exercise 56: initial cost Rs 770,000, annual inflow Rs 121,000 for 3 years, discount rate 16%. NPV is approximately

    1. A Rs 271,753
    2. B Rs -770,000
    3. C Rs -498,247
    4. D Rs -538,247
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  73. Q73 medium

    Capital budgeting analysis 57 for solar power plant project must correctly treat mutually exclusive replacement choice by

    1. A capitalizing all historical costs into initial outlay
    2. B comparing incremental cash flows of new versus continuing old equipment
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 57: mutually exclusive replacement choice for solar power plant.

  74. Q74 Past Paper · PPSC/FPSC/NTS hard

    NPV exercise 58: initial cost Rs 769,000, annual inflow Rs 128,600 for 5 years, discount rate 10%. NPV is approximately

    1. A Rs 487,495
    2. B Rs -769,000
    3. C Rs -321,505
    4. D Rs -281,505
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  75. Q75 medium

    Capital budgeting analysis 59 for warehouse automation project must correctly treat mutually exclusive replacement choice by

    1. A capitalizing all historical costs into initial outlay
    2. B comparing incremental cash flows of new versus continuing old equipment
    3. C using accounting net income without adjustment
    4. D ignoring terminal year cash flows entirely
    💡 Explanation:

    Project 59: mutually exclusive replacement choice for warehouse automation.