Capital Budgeting MCQs 2026
75 questions with detailed answers · 29 from past papers · 8 quiz batches available
Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 75 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
- Q1 Past Paper · PPSC/FPSC/NTS easy
Net Present Value (NPV) criterion accepts a standalone project when
💡 Explanation:Positive NPV adds shareholder value.
- Q2 Past Paper · PPSC/FPSC/NTS easy
Internal Rate of Return (IRR) is the discount rate that makes
💡 Explanation:IRR solves NPV=0 for r.
- Q3 medium
Profitability Index equals
💡 Explanation:PI = PV benefits / PV costs.
- Q4 Past Paper · PPSC/FPSC/NTS medium
Payback period ignores
💡 Explanation:Payback is a liquidity, not value, measure.
- Q5 medium
Discounted payback period improves on simple payback by
💡 Explanation:Time value incorporated in discounted payback.
- Q6 Past Paper · PPSC/FPSC/NTS hard
Mutually exclusive projects should be ranked by
💡 Explanation:IRR may conflict with NPV for mutually exclusive projects.
- Q7 medium
Capital rationing exists when
💡 Explanation:Firm cannot accept all value-adding projects.
- Q8 Past Paper · PPSC/FPSC/NTS medium
Sunk costs in capital budgeting are
💡 Explanation:Only incremental future cash flows matter.
- Q9 medium
Opportunity cost of using owned land for a project is
💡 Explanation:Opportunity cost is an economic concept.
- Q10 Past Paper · PPSC/FPSC/NTS hard
Terminal year cash flow in NPV analysis typically includes
💡 Explanation:Incremental terminal flows affect NPV.
- Q11 medium
Replacement decision analysis uses
💡 Explanation:Compare incremental inflows and outflows.
- Q12 Past Paper · PPSC/FPSC/NTS medium
Scenario analysis in capital budgeting varies
💡 Explanation:Tests sensitivity to plausible scenarios.
- Q13 hard
Real options in capital budgeting include
💡 Explanation:Flexibility has option value.
- Q14 Past Paper · PPSC/FPSC/NTS hard
Equivalent Annual Annuity approach helps compare projects with
💡 Explanation:EAA converts NPV to annuity equivalent.
- Q15 hard
Inflation in cash flow forecasting requires
💡 Explanation:Real/nominal consistency is essential.
- Q16 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 20: initial cost Rs 333,000, annual inflow Rs 64,200 for 7 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q17 medium
Capital budgeting analysis 21 for ERP system project must correctly treat depreciation tax shield by
💡 Explanation:Project 21: depreciation tax shield for ERP system.
- Q18 hard
NPV exercise 22: initial cost Rs 332,000, annual inflow Rs 61,800 for 4 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q19 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 23 for waste treatment facility project must correctly treat depreciation tax shield by
💡 Explanation:Project 23: depreciation tax shield for waste treatment facility.
- Q20 hard
NPV exercise 24: initial cost Rs 366,000, annual inflow Rs 69,400 for 6 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q21 hard
Capital budgeting analysis 25 for solar power plant project must correctly treat opportunity cost of land by
💡 Explanation:Project 25: opportunity cost of land for solar power plant.
- Q22 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 26: initial cost Rs 400,000, annual inflow Rs 67,000 for 3 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q23 medium
Capital budgeting analysis 27 for warehouse automation project must correctly treat opportunity cost of land by
💡 Explanation:Project 27: opportunity cost of land for warehouse automation.
- Q24 hard
NPV exercise 28: initial cost Rs 434,000, annual inflow Rs 74,600 for 5 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q25 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 29 for ERP system project must correctly treat opportunity cost of land by
💡 Explanation:Project 29: opportunity cost of land for ERP system.
- Q26 hard
NPV exercise 30: initial cost Rs 433,000, annual inflow Rs 82,200 for 7 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q27 hard
Capital budgeting analysis 31 for waste treatment facility project must correctly treat opportunity cost of land by
💡 Explanation:Project 31: opportunity cost of land for waste treatment facility.
- Q28 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 32: initial cost Rs 467,000, annual inflow Rs 79,800 for 4 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q29 medium
Capital budgeting analysis 33 for solar power plant project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 33: sunk R&D costs treatment for solar power plant.
- Q30 hard
NPV exercise 34: initial cost Rs 501,000, annual inflow Rs 87,400 for 6 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q31 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 35 for warehouse automation project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 35: sunk R&D costs treatment for warehouse automation.
- Q32 hard
NPV exercise 36: initial cost Rs 500,000, annual inflow Rs 85,000 for 3 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q33 Past Paper · PPSC/FPSC/NTS hard
Capital budgeting analysis 37 for ERP system project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 37: sunk R&D costs treatment for ERP system.
- Q34 hard
NPV exercise 38: initial cost Rs 534,000, annual inflow Rs 92,600 for 5 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q35 medium
Capital budgeting analysis 39 for waste treatment facility project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 39: sunk R&D costs treatment for waste treatment facility.
- Q36 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 40: initial cost Rs 568,000, annual inflow Rs 100,200 for 7 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q37 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 60: initial cost Rs 803,000, annual inflow Rs 136,200 for 7 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q38 medium
Capital budgeting analysis 41 for solar power plant project must correctly treat inflation in cash flows by
💡 Explanation:Project 41: inflation in cash flows for solar power plant.
- Q39 hard
Capital budgeting analysis 1 for solar power plant project must correctly treat salvage value estimation by
💡 Explanation:Project 1: salvage value estimation for solar power plant.
- Q40 hard
NPV exercise 2: initial cost Rs 97,000, annual inflow Rs 25,800 for 4 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q41 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 3 for warehouse automation project must correctly treat salvage value estimation by
💡 Explanation:Project 3: salvage value estimation for warehouse automation.
- Q42 hard
NPV exercise 4: initial cost Rs 131,000, annual inflow Rs 33,400 for 6 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q43 medium
Capital budgeting analysis 5 for ERP system project must correctly treat salvage value estimation by
💡 Explanation:Project 5: salvage value estimation for ERP system.
- Q44 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 6: initial cost Rs 165,000, annual inflow Rs 31,000 for 3 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q45 hard
Capital budgeting analysis 7 for waste treatment facility project must correctly treat salvage value estimation by
💡 Explanation:Project 7: salvage value estimation for waste treatment facility.
- Q46 hard
NPV exercise 8: initial cost Rs 164,000, annual inflow Rs 38,600 for 5 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q47 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 9 for solar power plant project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 9: working capital recovery in terminal year for solar power plant.
- Q48 hard
NPV exercise 10: initial cost Rs 198,000, annual inflow Rs 46,200 for 7 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q49 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 11 for warehouse automation project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 11: working capital recovery in terminal year for warehouse automation.
- Q50 hard
NPV exercise 12: initial cost Rs 232,000, annual inflow Rs 43,800 for 4 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q51 hard
Capital budgeting analysis 13 for ERP system project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 13: working capital recovery in terminal year for ERP system.
- Q52 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 14: initial cost Rs 266,000, annual inflow Rs 51,400 for 6 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q53 medium
Capital budgeting analysis 15 for waste treatment facility project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 15: working capital recovery in terminal year for waste treatment facility.
- Q54 hard
NPV exercise 16: initial cost Rs 265,000, annual inflow Rs 49,000 for 3 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q55 Past Paper · PPSC/FPSC/NTS medium
Capital budgeting analysis 17 for solar power plant project must correctly treat depreciation tax shield by
💡 Explanation:Project 17: depreciation tax shield for solar power plant.
- Q56 hard
NPV exercise 18: initial cost Rs 299,000, annual inflow Rs 56,600 for 5 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q57 hard
Capital budgeting analysis 19 for warehouse automation project must correctly treat depreciation tax shield by
💡 Explanation:Project 19: depreciation tax shield for warehouse automation.
- Q58 hard
NPV exercise 42: initial cost Rs 602,000, annual inflow Rs 97,800 for 4 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q59 Past Paper · PPSC/FPSC/NTS hard
Capital budgeting analysis 43 for warehouse automation project must correctly treat inflation in cash flows by
💡 Explanation:Project 43: inflation in cash flows for warehouse automation.
- Q60 hard
NPV exercise 44: initial cost Rs 601,000, annual inflow Rs 105,400 for 6 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q61 medium
Capital budgeting analysis 45 for ERP system project must correctly treat inflation in cash flows by
💡 Explanation:Project 45: inflation in cash flows for ERP system.
- Q62 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 46: initial cost Rs 635,000, annual inflow Rs 103,000 for 3 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q63 medium
Capital budgeting analysis 47 for waste treatment facility project must correctly treat inflation in cash flows by
💡 Explanation:Project 47: inflation in cash flows for waste treatment facility.
- Q64 hard
NPV exercise 48: initial cost Rs 669,000, annual inflow Rs 110,600 for 5 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q65 Past Paper · PPSC/FPSC/NTS hard
Capital budgeting analysis 49 for solar power plant project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 49: risk-adjusted discount rate for solar power plant.
- Q66 hard
NPV exercise 50: initial cost Rs 668,000, annual inflow Rs 118,200 for 7 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q67 medium
Capital budgeting analysis 51 for warehouse automation project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 51: risk-adjusted discount rate for warehouse automation.
- Q68 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 52: initial cost Rs 702,000, annual inflow Rs 115,800 for 4 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q69 medium
Capital budgeting analysis 53 for ERP system project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 53: risk-adjusted discount rate for ERP system.
- Q70 hard
NPV exercise 54: initial cost Rs 736,000, annual inflow Rs 123,400 for 6 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q71 Past Paper · PPSC/FPSC/NTS hard
Capital budgeting analysis 55 for waste treatment facility project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 55: risk-adjusted discount rate for waste treatment facility.
- Q72 hard
NPV exercise 56: initial cost Rs 770,000, annual inflow Rs 121,000 for 3 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q73 medium
Capital budgeting analysis 57 for solar power plant project must correctly treat mutually exclusive replacement choice by
💡 Explanation:Project 57: mutually exclusive replacement choice for solar power plant.
- Q74 Past Paper · PPSC/FPSC/NTS hard
NPV exercise 58: initial cost Rs 769,000, annual inflow Rs 128,600 for 5 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q75 medium
Capital budgeting analysis 59 for warehouse automation project must correctly treat mutually exclusive replacement choice by
💡 Explanation:Project 59: mutually exclusive replacement choice for warehouse automation.