Capital Budgeting MCQs 2026
75 questions with detailed answers · 29 from past papers · 8 quiz batches available
Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 75 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
- Q1Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 35 for warehouse automation project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 35: sunk R&D costs treatment for warehouse automation.
- Q2Past Paper · PPSC/FPSC/NTSeasy
Net Present Value (NPV) criterion accepts a standalone project when
💡 Explanation:Positive NPV adds shareholder value.
- Q3Past Paper · PPSC/FPSC/NTSeasy
Internal Rate of Return (IRR) is the discount rate that makes
💡 Explanation:IRR solves NPV=0 for r.
- Q4medium
Profitability Index equals
💡 Explanation:PI = PV benefits / PV costs.
- Q5Past Paper · PPSC/FPSC/NTSmedium
Payback period ignores
💡 Explanation:Payback is a liquidity, not value, measure.
- Q6medium
Discounted payback period improves on simple payback by
💡 Explanation:Time value incorporated in discounted payback.
- Q7Past Paper · PPSC/FPSC/NTShard
Mutually exclusive projects should be ranked by
💡 Explanation:IRR may conflict with NPV for mutually exclusive projects.
- Q8medium
Capital rationing exists when
💡 Explanation:Firm cannot accept all value-adding projects.
- Q9Past Paper · PPSC/FPSC/NTSmedium
Sunk costs in capital budgeting are
💡 Explanation:Only incremental future cash flows matter.
- Q10medium
Opportunity cost of using owned land for a project is
💡 Explanation:Opportunity cost is an economic concept.
- Q11Past Paper · PPSC/FPSC/NTShard
Terminal year cash flow in NPV analysis typically includes
💡 Explanation:Incremental terminal flows affect NPV.
- Q12medium
Replacement decision analysis uses
💡 Explanation:Compare incremental inflows and outflows.
- Q13Past Paper · PPSC/FPSC/NTSmedium
Scenario analysis in capital budgeting varies
💡 Explanation:Tests sensitivity to plausible scenarios.
- Q14hard
Real options in capital budgeting include
💡 Explanation:Flexibility has option value.
- Q15Past Paper · PPSC/FPSC/NTShard
Equivalent Annual Annuity approach helps compare projects with
💡 Explanation:EAA converts NPV to annuity equivalent.
- Q16hard
Inflation in cash flow forecasting requires
💡 Explanation:Real/nominal consistency is essential.
- Q17Past Paper · PPSC/FPSC/NTShard
NPV exercise 20: initial cost Rs 333,000, annual inflow Rs 64,200 for 7 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q18medium
Capital budgeting analysis 21 for ERP system project must correctly treat depreciation tax shield by
💡 Explanation:Project 21: depreciation tax shield for ERP system.
- Q19hard
NPV exercise 22: initial cost Rs 332,000, annual inflow Rs 61,800 for 4 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q20Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 23 for waste treatment facility project must correctly treat depreciation tax shield by
💡 Explanation:Project 23: depreciation tax shield for waste treatment facility.
- Q21hard
NPV exercise 24: initial cost Rs 366,000, annual inflow Rs 69,400 for 6 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q22hard
Capital budgeting analysis 25 for solar power plant project must correctly treat opportunity cost of land by
💡 Explanation:Project 25: opportunity cost of land for solar power plant.
- Q23Past Paper · PPSC/FPSC/NTShard
NPV exercise 26: initial cost Rs 400,000, annual inflow Rs 67,000 for 3 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q24medium
Capital budgeting analysis 27 for warehouse automation project must correctly treat opportunity cost of land by
💡 Explanation:Project 27: opportunity cost of land for warehouse automation.
- Q25hard
NPV exercise 28: initial cost Rs 434,000, annual inflow Rs 74,600 for 5 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q26Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 29 for ERP system project must correctly treat opportunity cost of land by
💡 Explanation:Project 29: opportunity cost of land for ERP system.
- Q27hard
NPV exercise 30: initial cost Rs 433,000, annual inflow Rs 82,200 for 7 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q28hard
Capital budgeting analysis 31 for waste treatment facility project must correctly treat opportunity cost of land by
💡 Explanation:Project 31: opportunity cost of land for waste treatment facility.
- Q29Past Paper · PPSC/FPSC/NTShard
NPV exercise 32: initial cost Rs 467,000, annual inflow Rs 79,800 for 4 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q30medium
Capital budgeting analysis 33 for solar power plant project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 33: sunk R&D costs treatment for solar power plant.
- Q31hard
NPV exercise 34: initial cost Rs 501,000, annual inflow Rs 87,400 for 6 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q32hard
NPV exercise 36: initial cost Rs 500,000, annual inflow Rs 85,000 for 3 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q33Past Paper · PPSC/FPSC/NTShard
Capital budgeting analysis 37 for ERP system project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 37: sunk R&D costs treatment for ERP system.
- Q34hard
NPV exercise 38: initial cost Rs 534,000, annual inflow Rs 92,600 for 5 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q35medium
Capital budgeting analysis 39 for waste treatment facility project must correctly treat sunk R&D costs treatment by
💡 Explanation:Project 39: sunk R&D costs treatment for waste treatment facility.
- Q36Past Paper · PPSC/FPSC/NTShard
NPV exercise 40: initial cost Rs 568,000, annual inflow Rs 100,200 for 7 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q37medium
Capital budgeting analysis 41 for solar power plant project must correctly treat inflation in cash flows by
💡 Explanation:Project 41: inflation in cash flows for solar power plant.
- Q38hard
NPV exercise 42: initial cost Rs 602,000, annual inflow Rs 97,800 for 4 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q39Past Paper · PPSC/FPSC/NTShard
Capital budgeting analysis 43 for warehouse automation project must correctly treat inflation in cash flows by
💡 Explanation:Project 43: inflation in cash flows for warehouse automation.
- Q40hard
NPV exercise 44: initial cost Rs 601,000, annual inflow Rs 105,400 for 6 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q41medium
Capital budgeting analysis 45 for ERP system project must correctly treat inflation in cash flows by
💡 Explanation:Project 45: inflation in cash flows for ERP system.
- Q42Past Paper · PPSC/FPSC/NTShard
NPV exercise 46: initial cost Rs 635,000, annual inflow Rs 103,000 for 3 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q43medium
Capital budgeting analysis 47 for waste treatment facility project must correctly treat inflation in cash flows by
💡 Explanation:Project 47: inflation in cash flows for waste treatment facility.
- Q44hard
NPV exercise 48: initial cost Rs 669,000, annual inflow Rs 110,600 for 5 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q45Past Paper · PPSC/FPSC/NTShard
Capital budgeting analysis 49 for solar power plant project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 49: risk-adjusted discount rate for solar power plant.
- Q46hard
NPV exercise 50: initial cost Rs 668,000, annual inflow Rs 118,200 for 7 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q47medium
Capital budgeting analysis 51 for warehouse automation project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 51: risk-adjusted discount rate for warehouse automation.
- Q48Past Paper · PPSC/FPSC/NTShard
NPV exercise 52: initial cost Rs 702,000, annual inflow Rs 115,800 for 4 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q49medium
Capital budgeting analysis 53 for ERP system project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 53: risk-adjusted discount rate for ERP system.
- Q50hard
NPV exercise 54: initial cost Rs 736,000, annual inflow Rs 123,400 for 6 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q51Past Paper · PPSC/FPSC/NTShard
Capital budgeting analysis 55 for waste treatment facility project must correctly treat risk-adjusted discount rate by
💡 Explanation:Project 55: risk-adjusted discount rate for waste treatment facility.
- Q52hard
NPV exercise 56: initial cost Rs 770,000, annual inflow Rs 121,000 for 3 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q53medium
Capital budgeting analysis 57 for solar power plant project must correctly treat mutually exclusive replacement choice by
💡 Explanation:Project 57: mutually exclusive replacement choice for solar power plant.
- Q54Past Paper · PPSC/FPSC/NTShard
NPV exercise 58: initial cost Rs 769,000, annual inflow Rs 128,600 for 5 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q55medium
Capital budgeting analysis 59 for warehouse automation project must correctly treat mutually exclusive replacement choice by
💡 Explanation:Project 59: mutually exclusive replacement choice for warehouse automation.
- Q56hard
Capital budgeting analysis 1 for solar power plant project must correctly treat salvage value estimation by
💡 Explanation:Project 1: salvage value estimation for solar power plant.
- Q57hard
NPV exercise 2: initial cost Rs 97,000, annual inflow Rs 25,800 for 4 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q58Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 3 for warehouse automation project must correctly treat salvage value estimation by
💡 Explanation:Project 3: salvage value estimation for warehouse automation.
- Q59hard
NPV exercise 4: initial cost Rs 131,000, annual inflow Rs 33,400 for 6 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q60medium
Capital budgeting analysis 5 for ERP system project must correctly treat salvage value estimation by
💡 Explanation:Project 5: salvage value estimation for ERP system.
- Q61Past Paper · PPSC/FPSC/NTShard
NPV exercise 6: initial cost Rs 165,000, annual inflow Rs 31,000 for 3 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q62hard
Capital budgeting analysis 7 for waste treatment facility project must correctly treat salvage value estimation by
💡 Explanation:Project 7: salvage value estimation for waste treatment facility.
- Q63hard
NPV exercise 8: initial cost Rs 164,000, annual inflow Rs 38,600 for 5 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q64Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 9 for solar power plant project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 9: working capital recovery in terminal year for solar power plant.
- Q65hard
NPV exercise 10: initial cost Rs 198,000, annual inflow Rs 46,200 for 7 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q66Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 11 for warehouse automation project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 11: working capital recovery in terminal year for warehouse automation.
- Q67hard
NPV exercise 12: initial cost Rs 232,000, annual inflow Rs 43,800 for 4 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q68hard
Capital budgeting analysis 13 for ERP system project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 13: working capital recovery in terminal year for ERP system.
- Q69Past Paper · PPSC/FPSC/NTShard
NPV exercise 14: initial cost Rs 266,000, annual inflow Rs 51,400 for 6 years, discount rate 14%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q70medium
Capital budgeting analysis 15 for waste treatment facility project must correctly treat working capital recovery in terminal year by
💡 Explanation:Project 15: working capital recovery in terminal year for waste treatment facility.
- Q71hard
NPV exercise 16: initial cost Rs 265,000, annual inflow Rs 49,000 for 3 years, discount rate 16%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q72Past Paper · PPSC/FPSC/NTSmedium
Capital budgeting analysis 17 for solar power plant project must correctly treat depreciation tax shield by
💡 Explanation:Project 17: depreciation tax shield for solar power plant.
- Q73hard
NPV exercise 18: initial cost Rs 299,000, annual inflow Rs 56,600 for 5 years, discount rate 10%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.
- Q74hard
Capital budgeting analysis 19 for warehouse automation project must correctly treat depreciation tax shield by
💡 Explanation:Project 19: depreciation tax shield for warehouse automation.
- Q75Past Paper · PPSC/FPSC/NTShard
NPV exercise 60: initial cost Rs 803,000, annual inflow Rs 136,200 for 7 years, discount rate 12%. NPV is approximately
💡 Explanation:Sum discounted inflows minus initial investment.