Earthing, Safety and Pakistan Grid Practices MCQs 2026

50 questions with detailed answers · 38 from past papers · 5 quiz batches available

📚 Electrical Engineering 📄 38 Past-Paper Qs ✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1 Questions 110 of 50
  1. Q1 medium

    Minimum size of main earthing conductor in many codes depends on

    1. A only lamp wattage
    2. B largest incoming service conductor and fault level
    3. C only motor color code
    4. D only cable brand name
    💡 Explanation:

    Cross-section must carry prospective earth fault current.

  2. Q2 Past Paper · PPSC/FPSC/NTS easy

    Earth Leakage Circuit Breaker (ELCB) detects

    1. A only overvoltage on lighting circuit
    2. B imbalance indicating leakage current to earth
    3. C only motor rpm
    4. D only transformer flux density
    💡 Explanation:

    Core-balance or voltage-operated types sense earth leakage.

  3. Q3 Past Paper · PPSC/FPSC/NTS easy

    Residual Current Device (RCD) operates when

    1. A load power factor is unity only
    2. B voltage is exactly 230 V
    3. C motor is underloaded
    4. D vector sum of line currents deviates from zero (leakage to earth)
    💡 Explanation:

    Differential current through toroidal core trips device.

  4. Q4 Past Paper · PPSC/FPSC/NTS easy

    Standard residential RCD sensitivity is often

    1. A 300 A
    2. B 30 A
    3. C 30 mA for additional protection against shock
    4. D 3 A
    💡 Explanation:

    30 mA limits shock duration/current for wet locations.

  5. Q5 Past Paper · PPSC/FPSC/NTS medium

    RCD does not replace

    1. A overcurrent protection (MCB/fuse) for short circuit and overload
    2. B need for earthing
    3. C insulation on conductors
    4. D correct wiring polarity checks
    💡 Explanation:

    RCD handles leakage; MCB handles overcurrent.

  6. Q6 medium

    Voltage-operated ELCB is largely superseded because

    1. A it is always faster than 1 ms
    2. B it depends on rise of earth voltage and may be less reliable
    3. C it eliminates need for earthing
    4. D it measures only DC traction current
    💡 Explanation:

    Current-balance RCD is preferred in modern installations.

  7. Q7 Past Paper · PPSC/FPSC/NTS medium

    RCD nuisance tripping may be caused by

    1. A perfect insulation with zero leakage always
    2. B unity power factor alone
    3. C correct TN-S wiring only
    4. D cumulative leakage from filters, capacitors and damp equipment
    💡 Explanation:

    Equipment capacitive leakage can approach 30 mA threshold.

  8. Q8 hard

    Selective (time-graded) RCD coordination uses

    1. A all 30 mA instant on main incomer only
    2. B no earthing on sub-circuits
    3. C higher sensitivity downstream and delayed upstream devices
    4. D only fuse without any RCD
    💡 Explanation:

    Discrimination limits outage to faulted circuit.

  9. Q9 easy

    RCD test button creates

    1. A permanent short of phase to neutral for load
    2. B simulated imbalance to verify mechanical trip function
    3. C open-circuit of earth electrode
    4. D increase of supply voltage to 440 V
    💡 Explanation:

    Monthly user test confirms trip mechanism operates.

  10. Q10 Past Paper · PPSC/FPSC/NTS medium

    IEC 60439 / modern switchgear may use RCBO which combines

    1. A overcurrent protection and residual current protection in one device
    2. B only lighting dimmer
    3. C only surge arrester without MCB
    4. D only ammeter shunt
    💡 Explanation:

    RCBO protects cable and persons on same pole.

  11. Q11 Past Paper · PPSC/FPSC/NTS hard

    30 mA RCD may not detect

    1. A line-to-line fault if no earth path involved (unlikely on earthed systems)
    2. B line-to-earth fault through person
    3. C leakage via damaged cable to wet floor
    4. D appliance frame fault to PE
    💡 Explanation:

    RCD needs earth leakage path; MCB clears line faults.

  12. Q12 hard

    Type AC RCD is suitable for

    1. A pure DC leakage only without AC component
    2. B high-frequency PWM without Type A/B consideration
    3. C sinusoidal AC residual currents
    4. D only lightning impulse without evaluation
    💡 Explanation:

    Type A/B/AEV address pulsating DC and HF applications.

  13. Q13 Past Paper · PPSC/FPSC/NTS medium

    ELCB/RCD must be connected such that

    1. A neutral bypasses sensor always
    2. B earth wire carries load current intentionally
    3. C all live conductors pass through the toroidal sensor
    4. D phase is left out of sensor
    💡 Explanation:

    Differential sensing requires all current-carrying wires through core.

  14. Q14 Past Paper · PPSC/FPSC/NTS medium

    In TT installations RCD is often mandatory because

    1. A earth resistance is always zero
    2. B earth fault loop impedance may be too high for fast MCB disconnection
    3. C neutral is solidly earthed at consumer
    4. D no touch voltage can exist
    💡 Explanation:

    RCD clears faults at low leakage current without low Zs.

  15. Q15 Past Paper · PPSC/FPSC/NTS easy

    RCD rated residual operating current IΔn is

    1. A the load current rating In only
    2. B the leakage current at which the device must trip
    3. C the breaking capacity in kA only
    4. D the lamp lumen output
    💡 Explanation:

    IΔn (e.g., 30 mA, 100 mA, 300 mA) sets sensitivity class.

  16. Q16 hard

    Fire protection RCDs may be rated

    1. A 300 mA with time delay for discrimination
    2. B 30 mA on entire factory incomer without grading
    3. C 3 A residual only
    4. D without any earthing
    💡 Explanation:

    Higher threshold prevents nuisance trips on leakage capacitance.

  17. Q17 Past Paper · PPSC/FPSC/NTS medium

    Periodic inspection of RCD includes

    1. A trip time test at rated residual current per IEC 61557
    2. B only painting enclosure
    3. C only tightening lamp holder
    4. D only measuring lux level
    💡 Explanation:

    Test equipment verifies trip within specified milliseconds.

  18. Q18 Past Paper · PPSC/FPSC/NTS easy

    NEPRA in Pakistan regulates

    1. A only telecommunications spectrum
    2. B only water supply tariffs
    3. C electric power sector including licensing and consumer protection standards
    4. D only aviation fuel pricing
    💡 Explanation:

    National Electric Power Regulatory Authority oversees electricity market.

  19. Q19 Past Paper · PPSC/FPSC/NTS easy

    NTDC operates

    1. A only domestic house wiring
    2. B only diesel generator retail sales
    3. C only street lighting design
    4. D national transmission grid and bulk power dispatch in Pakistan
    💡 Explanation:

    National Transmission and Despatch Company manages EHV network.

  20. Q20 Past Paper · PPSC/FPSC/NTS medium

    Grid Code issued under NEPRA framework defines

    1. A technical and safety requirements for grid-connected parties
    2. B only color of insulators without electrical limits
    3. C only welding electrode sizes
    4. D only lamp CRI values
    💡 Explanation:

    Grid code sets voltage, fault ride-through, protection and metering rules.

  21. Q21 Past Paper · PPSC/FPSC/NTS medium

    Permissible voltage variation at consumer terminals in many standards is approximately

    1. A ±6% or as per applicable regulation
    2. B ±50% without limit
    3. C exactly 0% always
    4. D ±30% for all loads
    💡 Explanation:

    Voltage quality clauses protect equipment and service quality.

  22. Q22 Past Paper · PPSC/FPSC/NTS easy

    Safety clearance from live overhead lines for workers is governed by

    1. A only luminaire spacing tables
    2. B NTDC/utility safety rules and IE Rules aligned practices
    3. C only motor nameplate only
    4. D only cable color mnemonic
    💡 Explanation:

    Approach distances depend on voltage level.

  23. Q23 Past Paper · PPSC/FPSC/NTS easy

    Consumer earthing inspection under distribution safety rules checks

    1. A only decorative wiring
    2. B only highest lamp wattage
    3. C only motor paint color
    4. D earth electrode resistance, bonding and RCD operation
    💡 Explanation:

    DISCOs enforce safe installation practices at service.

  24. Q24 Past Paper · PPSC/FPSC/NTS easy

    Working near exposed busbars in substation requires

    1. A conductive jewelry for convenience
    2. B wet cotton gloves only
    3. C arc-rated clothing and insulated tools per hazard assessment
    4. D no barricades ever
    💡 Explanation:

    EHV environments demand rigorous PPE and procedure.

  25. Q25 Past Paper · PPSC/FPSC/NTS easy

    Grid frequency in Pakistan is nominally

    1. A 60 Hz always without exception
    2. B 25 Hz for all transmission
    3. C 400 Hz for distribution
    4. D 50 Hz with operational limits per grid code
    💡 Explanation:

    Synchronized area operates at 50 Hz like much of Asia/Europe.

  26. Q26 Past Paper · PPSC/FPSC/NTS medium

    Safety tagging on isolated NTDC circuits uses

    1. A green tag meaning energize
    2. B no documentation
    3. C tags on unrelated feeders only
    4. D danger tags and earth tags after proven dead and earthed
    💡 Explanation:

    Tag system communicates status to all personnel.

  27. Q27 hard

    Incident energy study for NTDC/DISCO switchgear supports

    1. A only lamp maintenance factor
    2. B selection of arc-flash PPE and safe working distances
    3. C only motor slip calculation
    4. D only cable charging MVAR
    💡 Explanation:

    Arc flash hazard analysis protects maintenance staff.

  28. Q28 Past Paper · PPSC/FPSC/NTS hard

    Earthing of NTDC substation structures and equipment follows

    1. A only single 1 ohm rod without study
    2. B engineered earth grid design for fault current and touch/step limits
    3. C floating earth without reference
    4. D connection to phase conductor
    💡 Explanation:

    IEEE 80 / IEC practices model grid resistance and gradients.

  29. Q29 Past Paper · PPSC/FPSC/NTS medium

    Protection coordination on NTDC grid ensures

    1. A all breakers trip on any fault simultaneously always
    2. B no relay settings ever changed
    3. C fault cleared by nearest breaker with backup discrimination
    4. D only fuse protection on 500 kV
    💡 Explanation:

    Time and distance grading maintain stability and supply.

  30. Q30 Past Paper · PPSC/FPSC/NTS medium

    Authorization to work on NTDC substation equipment requires

    1. A only verbal agreement
    2. B direct energization for test without lockout
    3. C permit-to-work and isolation with earth application procedures
    4. D bypassing interlocks routinely
    💡 Explanation:

    Systematic LOTO prevents accidental re-energization.

  31. Q31 Past Paper · PPSC/FPSC/NTS medium

    Lightning protection earth should be

    1. A always completely isolated without bonding rules
    2. B connected only to phase conductor
    3. C bonded to power system earth where codes permit common electrode
    4. D left unconnected intentionally
    💡 Explanation:

    Coordinated bonding avoids dangerous potential differences.

  32. Q32 Past Paper · PPSC/FPSC/NTS hard

    Earth mat in substations is provided to

    1. A limit step and touch potentials during grid faults
    2. B increase fault current path impedance only
    3. C decorate switchyard only
    4. D replace insulation coordination
    💡 Explanation:

    Buried or surface mesh equalizes potential under EHV equipment.

  33. Q33 medium

    Chemical earthing (maintenance-free) uses

    1. A only dry sand without metal
    2. B conductive compounds around electrode to lower contact resistance
    3. C only insulating varnish on rod
    4. D only neon lamp gas
    💡 Explanation:

    Hygroscopic compounds keep moisture around electrode.

  34. Q34 Past Paper · PPSC/FPSC/NTS hard

    Step potential hazard near earth electrode during fault is

    1. A voltage across lamp filament only
    2. B flux in transformer core only
    3. C voltage difference between feet at different soil potentials
    4. D power factor of motor only
    💡 Explanation:

    Gradient in earth potential can shock personnel nearby.

  35. Q35 hard

    TN-C-S (PME) combines neutral and earth on supply side with

    1. A separate PE after split at consumer service
    2. B permanent combined PEN to all sockets without split
    3. C no earthing at transformer
    4. D only DC traction return
    💡 Explanation:

    PEN becomes separate N and PE at customer intake.

  36. Q36 Past Paper · PPSC/FPSC/NTS hard

    TT system earthing has

    1. A no earth electrode at all
    2. B phase and neutral shorted at load
    3. C only IT system without any earth
    4. D local earth electrode at consumer with utility neutral earthed separately
    💡 Explanation:

    TT relies on local R_A and RCD due to higher loop impedance.

  37. Q37 Past Paper · PPSC/FPSC/NTS medium

    Separate protective earth (PE) and neutral (N) must not be

    1. A combined after the main earthing terminal except as defined by TN-S rules
    2. B bonded at every socket always incorrectly
    3. C left floating on consumer side
    4. D connected only to phase
    💡 Explanation:

    TN-S keeps N and PE separate to avoid neutral current on earth paths.

  38. Q38 medium

    Ring earth electrode around building in IEC practice provides

    1. A more uniform earth potential and lower resistance
    2. B higher touch voltage always
    3. C no connection to main earthing terminal
    4. D only lightning without power earthing
    💡 Explanation:

    Ring in trench with electrodes improves contact area.

  39. Q39 Past Paper · PPSC/FPSC/NTS medium

    Measurement of earth resistance commonly uses

    1. A only voltmeter across open circuit
    2. B fall-of-potential (three-point) method
    3. C only wattmeter on lighting load
    4. D only oscilloscope on communication line
    💡 Explanation:

    Auxiliary electrode placement determines measured earth R.

  40. Q40 Past Paper · PPSC/FPSC/NTS medium

    Soil resistivity affects earth electrode resistance such that

    1. A resistivity has no effect
    2. B dry rocky soil always gives lowest R
    3. C only pipe length color matters
    4. D higher resistivity soil gives higher electrode resistance
    💡 Explanation:

    R_e ∝ ρ; measurement drives electrode design.

  41. Q41 Past Paper · PPSC/FPSC/NTS easy

    Earth continuity conductor (ECC) ensures

    1. A phase voltage appears on casing
    2. B metallic enclosures remain at earth potential during faults
    3. C neutral is never connected
    4. D fuses never blow
    💡 Explanation:

    ECC links exposed conductive parts to main earth.

  42. Q42 Past Paper · PPSC/FPSC/NTS medium

    IS/IEC practice requires main equipotential bonding to connect

    1. A only lighting switches
    2. B incoming metal services and structural metal to earth terminal
    3. C only decorative paint
    4. D only plastic pipes without metal
    💡 Explanation:

    Bonding limits potential differences during earth faults.

  43. Q43 Past Paper · PPSC/FPSC/NTS easy

    Plate earth electrode uses

    1. A only overhead conductor
    2. B only fluorescent lamp ballast
    3. C buried metal plate (GI or copper) in a pit with alternating layers of coke and salt
    4. D only transformer oil only
    💡 Explanation:

    Large plate area contacts soil to reduce resistance.

  44. Q44 Past Paper · PPSC/FPSC/NTS easy

    Pipe earth electrode is commonly made of

    1. A PVC conduit only
    2. B wooden pole only
    3. C air gap only
    4. D galvanized iron or copper pipe driven vertically into soil
    💡 Explanation:

    Metal pipe in moist soil forms electrode; backfill with salt/coal may lower R.

  45. Q45 Past Paper · PPSC/FPSC/NTS easy

    Earth electrode resistance should generally be

    1. A as high as possible
    2. B equal to load resistance
    3. C infinite for safety
    4. D as low as practicable per national code (often ≤1–5 Ω for small installations)
    💡 Explanation:

    Lower resistance improves fault clearance and touch voltage control.

  46. Q46 Past Paper · PPSC/FPSC/NTS easy

    Purpose of electrical earthing in installations is primarily to

    1. A provide a low-impedance path for fault current and limit touch voltage
    2. B increase line voltage for efficiency
    3. C eliminate need for overcurrent protection
    4. D store energy in soil
    💡 Explanation:

    Earthing enables protective devices to operate and reduces shock risk.

  47. Q47 Past Paper · PPSC/FPSC/NTS medium

    Distributed generator connecting to grid must meet NEPRA/NTDC requirements for

    1. A uncontrolled energization during outage
    2. B no circuit breaker at POI
    3. C anti-islanding, protection, metering and power quality
    4. D reverse power flow without study
    💡 Explanation:

    Interconnection standards protect grid and personnel.

  48. Q48 Past Paper · PPSC/FPSC/NTS hard

    Neutral earthing in transmission is often through

    1. A floating without any monitoring
    2. B direct connection to street lighting circuit
    3. C only ELCB at 30 mA on EHV bus
    4. D substation transformer neutral reactor/resistor or solid ground per study
    💡 Explanation:

    Grounding practice limits fault current and overvoltages.

  49. Q49 medium

    Live-line maintenance on transmission requires

    1. A any worker without PPE
    2. B shorting phase to earth without permit
    3. C ignoring weather limits always
    4. D trained crews, approved tools and safety distances per utility procedure
    💡 Explanation:

    Hot-line work follows strict NTDC safety manuals.

  50. Q50 medium

    Reporting of major grid disturbances to regulator supports

    1. A reliability monitoring and corrective investment under NEPRA framework
    2. B only internal memo without data
    3. C deletion of event records
    4. D no protection review
    💡 Explanation:

    Performance standards drive accountability.