Power System Analysis and Load Flow MCQs 2026
69 questions with detailed answers · 44 from past papers · 7 quiz batches available
Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 69 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
- Q1 medium
Removing a line from service updates Y-bus by
💡 Explanation:Topology changes alter incident admittances at affected nodes.
- Q2 Past Paper · PPSC/FPSC/NTS easy
Admittance matrix Y-bus of a power network relates
💡 Explanation:Y-bus is the fundamental linear network model for load-flow and fault studies.
- Q3 Past Paper · PPSC/FPSC/NTS medium
Diagonal element Yii of Y-bus equals
💡 Explanation:Self-admittance includes all branches incident on node i.
- Q4 Past Paper · PPSC/FPSC/NTS medium
Off-diagonal element Yij of Y-bus for i ≠ j with direct branch between nodes is
💡 Explanation:Mutual terms are −yij for single series branch between nodes.
- Q5 Past Paper · PPSC/FPSC/NTS easy
Y-bus of a large transmission network is typically
💡 Explanation:Sparse structure enables efficient solution algorithms.
- Q6 Past Paper · PPSC/FPSC/NTS hard
Including transformer off-nominal tap in Y-bus requires
💡 Explanation:Tap ratio a affects both magnitude and angle of transformer model.
- Q7 Past Paper · PPSC/FPSC/NTS medium
Line charging susceptance in π-model contributes to Y-bus as
💡 Explanation:Half-line charging is placed at each end in nominal π representation.
- Q8 Past Paper · PPSC/FPSC/NTS easy
Grounded shunt capacitor bank at a bus adds to Y-bus
💡 Explanation:Capacitor increases jB at the connected node.
- Q9 hard
Mutual coupling between transmission lines on same tower appears in Y-bus as
💡 Explanation:Line coupling links electrically distinct node pairs.
- Q10 Past Paper · PPSC/FPSC/NTS medium
Assembly of Y-bus from branch data is called
💡 Explanation:Each branch stamps its 2×2 (or larger) contribution into Y.
- Q11 Past Paper · PPSC/FPSC/NTS easy
Per unit system simplifies Y-bus construction because
💡 Explanation:Consistent MVA and kV bases normalize network elements.
- Q12 Past Paper · PPSC/FPSC/NTS medium
Singular Y-bus (no reference) occurs if
💡 Explanation:A reference node fixes one voltage magnitude and angle.
- Q13 Past Paper · PPSC/FPSC/NTS medium
Z-bus is related to Y-bus by
💡 Explanation:Driving-point and transfer impedances come from Z-bus.
- Q14 Past Paper · PPSC/FPSC/NTS medium
Modified Y-bus for fault studies may insert
💡 Explanation:Fault connection adds large admittance or alters network at fault point.
- Q15 hard
Three-phase Y-bus can be built from
💡 Explanation:Unbalanced systems may require coupled 3n×3n Y or sequence methods.
- Q16 Past Paper · PPSC/FPSC/NTS easy
Equivalent π parameters of a line branch for Y-bus come from
💡 Explanation:π model yields series y and shunt jB/2 at each end.
- Q17 Past Paper · PPSC/FPSC/NTS medium
PV bus treatment in NR includes
💡 Explanation:PV buses add P-specified equation and V magnitude constraint.
- Q18 hard
Ill-conditioned cases for NR include
💡 Explanation:Near singularity of J slows or stalls convergence.
- Q19 hard
Rectangular coordinates (e,f) alternative in NR uses
💡 Explanation:Rectangular form avoids trig in some formulations.
- Q20 hard
Optimal multiplier in NR can
💡 Explanation:Line search/optimal multiplier helps difficult cases.
- Q21 hard
After NR solution, LMP or marginal loss calculations may use
💡 Explanation:Post-convergence analytics use power flow Jacobian inverse sensitivities.
- Q22 hard
Continued power flow uses NR with parameterization to trace
💡 Explanation:CPF finds maximum loadability margin.
- Q23 Past Paper · PPSC/FPSC/NTS easy
NR is preferred in commercial EMS for
💡 Explanation:Industry standard for bulk power flow.
- Q24 hard
Symmetric Jacobian structure is not generally symmetric because
💡 Explanation:Full NR Jacobian is nonsymmetric though Y may be symmetric.
- Q25 Past Paper · PPSC/FPSC/NTS medium
Updating voltage in polar NR computes
💡 Explanation:Corrections added to current θ and V each iteration.
- Q26 medium
Flat start for NR on stiff EHV system may require
💡 Explanation:Difficult cases need engineering initial guesses or homotopy.
- Q27 hard
Transformer regulating tap change during NR may use
💡 Explanation:Tap is discrete; outer control adjusts tap after flow solution.
- Q28 medium
Loss allocation after NR can use
💡 Explanation:Loss formulas distribute line losses to generators/loads.
- Q29 Past Paper · PPSC/FPSC/NTS easy
Symmetrical three-phase fault has
💡 Explanation:Balanced fault simplifies to positive sequence network only.
- Q30 Past Paper · PPSC/FPSC/NTS medium
Line-to-line fault (LL) contains
💡 Explanation:LL is unbalanced but lacks zero sequence if system ungrounded.
- Q31 Past Paper · PPSC/FPSC/NTS medium
Sequence impedances Z1, Z2, Z0 are used to
💡 Explanation:Fortescue transformation decouples unbalanced networks.
- Q32 Past Paper · PPSC/FPSC/NTS easy
Fault MVA at a bus equals
💡 Explanation:Fault level indicates short-circuit severity for breaker rating.
- Q33 Past Paper · PPSC/FPSC/NTS medium
Subtransient reactance Xd″ of synchronous machine governs
💡 Explanation:Subtransient period has highest AC fault current from machines.
- Q34 hard
Transient reactance Xd′ is relevant for
💡 Explanation:Current transitions from subtransient to transient level.
- Q35 Past Paper · PPSC/FPSC/NTS medium
DC offset component in fault current arises from
💡 Explanation:Offset decays with armature L/R time constant.
- Q36 Past Paper · PPSC/FPSC/NTS hard
Breaker making capacity must withstand
💡 Explanation:First-cycle peak can be substantially above symmetrical peak.
- Q37 hard
Percentage DC component for breaker rating considers
💡 Explanation:High X/R yields slower offset decay and higher peak.
- Q38 Past Paper · PPSC/FPSC/NTS medium
Thevenin equivalent at fault bus for fault calculation uses
💡 Explanation:Vth and Zth simplify fault current computation.
- Q39 Past Paper · PPSC/FPSC/NTS easy
Solid fault means fault impedance is
💡 Explanation:Bolted fault assumes no additional impedance at fault point.
- Q40 Past Paper · PPSC/FPSC/NTS easy
Post-fault voltage sag severity depends on
💡 Explanation:Stiff networks show smaller voltage depression during faults.
- Q41 Past Paper · PPSC/FPSC/NTS medium
Bus impedance matrix (Z-bus) diagonal element Zii gives
💡 Explanation:Zii relates voltage at i to current injected at i.
- Q42 Past Paper · PPSC/FPSC/NTS medium
Distance relay measures
💡 Explanation:Z = V/I seen by relay estimates fault location.
- Q43 medium
Open conductor fault can cause
💡 Explanation:One or two open phases create severe unbalance.
- Q44 Past Paper · PPSC/FPSC/NTS medium
Fault through impedance (e.g., arc) reduces
💡 Explanation:Arc resistance limits current during fault.
- Q45 Past Paper · PPSC/FPSC/NTS medium
Fast decoupled load flow approximates Jacobian by
💡 Explanation:B′ and B″ matrices replace full Jacobian for speed.
- Q46 hard
Quadratic convergence of Newton-Raphson near solution means
💡 Explanation:Good initial guess yields very fast NR convergence.
- Q47 Past Paper · PPSC/FPSC/NTS hard
Jacobian matrix in NR contains partial derivatives of
💡 Explanation:J includes ∂P/∂θ, ∂P/∂V, ∂Q/∂θ, ∂Q/∂V blocks.
- Q48 Past Paper · PPSC/FPSC/NTS medium
Newton-Raphson load flow linearizes
💡 Explanation:NR solves ΔF = −J·Δx iteratively.
- Q49 hard
Distributed slack shares
💡 Explanation:Multiple slack generators share imbalance per defined weights.
- Q50 Past Paper · PPSC/FPSC/NTS easy
Stopping criterion for GS typically checks
💡 Explanation:max|ΔP|,|ΔQ| < ε across buses ends iteration.
- Q51 Past Paper · PPSC/FPSC/NTS medium
Mismatch at a bus in load flow is
💡 Explanation:ΔP and ΔQ drive iterative correction toward convergence.
- Q52 easy
Gauss-Seidel is attractive for teaching because
💡 Explanation:Educational simplicity; less used in large commercial tools than NR.
- Q53 Past Paper · PPSC/FPSC/NTS medium
After GS converges, line flows are computed from
💡 Explanation:Sij = Vi(Vi−Vj)Yij* etc. from solved voltages.
- Q54 easy
Number of iterations in GS depends on
💡 Explanation:Tighter ε and difficult cases need more passes.
- Q55 hard
Line charging and high R/X ratio can affect GS convergence by
💡 Explanation:Stiff networks favour Newton or fast decoupled methods.
- Q56 medium
Weakly meshed distribution feeders may converge with GS when
💡 Explanation:GS works for smaller or well-conditioned networks.
- Q57 medium
Gauss-Seidel update for PQ bus uses
💡 Explanation:Bus equations relate specified P,Q to surrounding voltages.
- Q58 Past Paper · PPSC/FPSC/NTS hard
Reactive power limit violation at PV bus during GS iteration requires
💡 Explanation:When Q hits limit, voltage can no longer be held; bus becomes PQ.
- Q59 Past Paper · PPSC/FPSC/NTS easy
Initial voltage guess for GS load flow often sets
💡 Explanation:Flat start is common unless better estimate available.
- Q60 Past Paper · PPSC/FPSC/NTS medium
Convergence of Gauss-Seidel is generally
💡 Explanation:NR quadratic convergence beats GS linear rate for tight tolerance.
- Q61 medium
Acceleration factor in Gauss-Seidel can
💡 Explanation:Over-relaxation (α > 1) may improve convergence rate.
- Q62 Past Paper · PPSC/FPSC/NTS medium
Gauss-Seidel method solves load flow by
💡 Explanation:GS uses most recent voltages when updating each bus sequentially.
- Q63 Past Paper · PPSC/FPSC/NTS easy
PQ bus in load flow specifies
💡 Explanation:Load buses have specified P and Q; V is unknown.
- Q64 Past Paper · PPSC/FPSC/NTS easy
Slack (swing) bus in load flow specifies
💡 Explanation:Slack absorbs mismatch in total P and Q generation vs load.
- Q65 Past Paper · PPSC/FPSC/NTS easy
PV bus in load flow specifies
💡 Explanation:PV (generator) bus controls P and V; Q varies to maintain V.
- Q66 Past Paper · PPSC/FPSC/NTS easy
Load-flow study computes
💡 Explanation:Steady-state power flow balances P and Q at each bus.
- Q67 hard
Phase-shifting transformer introduces in Y-bus
💡 Explanation:PSD flow controllers modify power flow via phase angle injection.
- Q68 Past Paper · PPSC/FPSC/NTS medium
Y-bus symmetry for passive network without phase shifters means
💡 Explanation:Reciprocal network admittance matrix is symmetric.
- Q69 medium
Sparsity techniques in NR exploit
💡 Explanation:Sparse LU factorization reduces memory and CPU.