Power System Analysis and Load Flow MCQs 2026

69 questions with detailed answers · 44 from past papers · 7 quiz batches available

📚 Electrical Engineering 📄 44 Past-Paper Qs ✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1 Questions 110 of 69
  1. Q1 medium

    Removing a line from service updates Y-bus by

    1. A inverting Z-bus only without change
    2. B multiplying all elements by zero
    3. C subtracting that branch stamp from the matrix
    4. D adding random entries
    💡 Explanation:

    Topology changes alter incident admittances at affected nodes.

  2. Q2 Past Paper · PPSC/FPSC/NTS easy

    Admittance matrix Y-bus of a power network relates

    1. A only real power to angle only without voltage
    2. B nodal current injections to nodal voltages via I = YV
    3. C only transformer losses to frequency
    4. D only cable tan delta to humidity
    💡 Explanation:

    Y-bus is the fundamental linear network model for load-flow and fault studies.

  3. Q3 Past Paper · PPSC/FPSC/NTS medium

    Diagonal element Yii of Y-bus equals

    1. A sum of all admittances connected to node i including shunt terms
    2. B only off-diagonal mutual terms
    3. C zero always
    4. D reciprocal of line length only
    💡 Explanation:

    Self-admittance includes all branches incident on node i.

  4. Q4 Past Paper · PPSC/FPSC/NTS medium

    Off-diagonal element Yij of Y-bus for i ≠ j with direct branch between nodes is

    1. A positive sum of all system admittances
    2. B always zero in any network
    3. C equal to transformer MVA only
    4. D negative of branch admittance between i and j
    💡 Explanation:

    Mutual terms are −yij for single series branch between nodes.

  5. Q5 Past Paper · PPSC/FPSC/NTS easy

    Y-bus of a large transmission network is typically

    1. A fully dense with all entries nonzero
    2. B diagonal only always
    3. C sparse because each node connects to few neighbours
    4. D identity matrix
    💡 Explanation:

    Sparse structure enables efficient solution algorithms.

  6. Q6 Past Paper · PPSC/FPSC/NTS hard

    Including transformer off-nominal tap in Y-bus requires

    1. A ignoring tap completely always
    2. B modifying effective admittance and sometimes phase shift
    3. C using only resistance of conductor
    4. D replacing Y with Z always
    💡 Explanation:

    Tap ratio a affects both magnitude and angle of transformer model.

  7. Q7 Past Paper · PPSC/FPSC/NTS medium

    Line charging susceptance in π-model contributes to Y-bus as

    1. A shunt admittance terms at line terminals
    2. B only series impedance without shunt
    3. C only DC resistance
    4. D only motor slip
    💡 Explanation:

    Half-line charging is placed at each end in nominal π representation.

  8. Q8 Past Paper · PPSC/FPSC/NTS easy

    Grounded shunt capacitor bank at a bus adds to Y-bus

    1. A positive susceptance on the diagonal of that bus
    2. B only off-diagonal mutual terms
    3. C negative resistance on all buses
    4. D zero change
    💡 Explanation:

    Capacitor increases jB at the connected node.

  9. Q9 hard

    Mutual coupling between transmission lines on same tower appears in Y-bus as

    1. A only diagonal elements
    2. B no effect in any case
    3. C off-diagonal terms between corresponding nodes
    4. D only in DC analysis
    💡 Explanation:

    Line coupling links electrically distinct node pairs.

  10. Q10 Past Paper · PPSC/FPSC/NTS medium

    Assembly of Y-bus from branch data is called

    1. A only Gauss-Seidel iteration
    2. B only per unit conversion of load only
    3. C only symmetrical component reduction
    4. D building by successive addition of branch stamp contributions
    💡 Explanation:

    Each branch stamps its 2×2 (or larger) contribution into Y.

  11. Q11 Past Paper · PPSC/FPSC/NTS easy

    Per unit system simplifies Y-bus construction because

    1. A all impedances become zero
    2. B branches on common bases add directly
    3. C voltage angles are eliminated
    4. D loads disappear
    💡 Explanation:

    Consistent MVA and kV bases normalize network elements.

  12. Q12 Past Paper · PPSC/FPSC/NTS medium

    Singular Y-bus (no reference) occurs if

    1. A all lines are lossless
    2. B all loads are unity PF
    3. C frequency is exactly 50 Hz
    4. D no ground/reference node is specified
    💡 Explanation:

    A reference node fixes one voltage magnitude and angle.

  13. Q13 Past Paper · PPSC/FPSC/NTS medium

    Z-bus is related to Y-bus by

    1. A simple transposition only
    2. B matrix inversion Z = Y⁻¹ for nonsingular Y
    3. C adding identity only
    4. D squaring each element
    💡 Explanation:

    Driving-point and transfer impedances come from Z-bus.

  14. Q14 Past Paper · PPSC/FPSC/NTS medium

    Modified Y-bus for fault studies may insert

    1. A fault admittance at faulted node
    2. B only transformer magnetizing branch removal
    3. C only solar irradiance data
    4. D only train mass
    💡 Explanation:

    Fault connection adds large admittance or alters network at fault point.

  15. Q15 hard

    Three-phase Y-bus can be built from

    1. A only single-phase without coupling ever
    2. B only DC battery model
    3. C phase network or from sequence networks with coupling
    4. D only corona loss formula
    💡 Explanation:

    Unbalanced systems may require coupled 3n×3n Y or sequence methods.

  16. Q16 Past Paper · PPSC/FPSC/NTS easy

    Equivalent π parameters of a line branch for Y-bus come from

    1. A series impedance and total shunt admittance of line model
    2. B only tower height
    3. C only insulator creepage
    4. D only VFD carrier frequency
    💡 Explanation:

    π model yields series y and shunt jB/2 at each end.

  17. Q17 Past Paper · PPSC/FPSC/NTS medium

    PV bus treatment in NR includes

    1. A equations for P and V with Q within limits
    2. B only Q and θ specified
    3. C no reactive power variable
    4. D fixed Q always
    💡 Explanation:

    PV buses add P-specified equation and V magnitude constraint.

  18. Q18 hard

    Ill-conditioned cases for NR include

    1. A unloaded open circuit only
    2. B heavy loading near voltage collapse and low impedance ties
    3. C single slack only
    4. D lossless lines only
    💡 Explanation:

    Near singularity of J slows or stalls convergence.

  19. Q19 hard

    Rectangular coordinates (e,f) alternative in NR uses

    1. A only magnitude without angle ever
    2. B only frequency deviation
    3. C real and imaginary parts of voltage instead of polar V,θ
    4. D only per unit resistance alone
    💡 Explanation:

    Rectangular form avoids trig in some formulations.

  20. Q20 hard

    Optimal multiplier in NR can

    1. A increase mismatch intentionally
    2. B remove Jacobian
    3. C fix all angles at zero
    4. D damp step size to improve global convergence
    💡 Explanation:

    Line search/optimal multiplier helps difficult cases.

  21. Q21 hard

    After NR solution, LMP or marginal loss calculations may use

    1. A solved voltages and sensitivity factors
    2. B only guesswork
    3. C only motor nameplate
    4. D only wind cut-out
    💡 Explanation:

    Post-convergence analytics use power flow Jacobian inverse sensitivities.

  22. Q22 hard

    Continued power flow uses NR with parameterization to trace

    1. A only transformer OC test
    2. B only cable tan delta
    3. C only VFD ramp
    4. D P-V nose curve toward voltage collapse point
    💡 Explanation:

    CPF finds maximum loadability margin.

  23. Q23 Past Paper · PPSC/FPSC/NTS easy

    NR is preferred in commercial EMS for

    1. A smallest possible 2-bus homework only always
    2. B reliable fast convergence on large transmission networks
    3. C systems without any nonlinearities
    4. D DC circuits only
    💡 Explanation:

    Industry standard for bulk power flow.

  24. Q24 hard

    Symmetric Jacobian structure is not generally symmetric because

    1. A Y-bus is complex
    2. B all loads are zero
    3. C mixing of P and Q equations with θ and V variables breaks symmetry
    4. D frequency is variable
    💡 Explanation:

    Full NR Jacobian is nonsymmetric though Y may be symmetric.

  25. Q25 Past Paper · PPSC/FPSC/NTS medium

    Updating voltage in polar NR computes

    1. A corrections Δθ and ΔV/ V from solved linear system
    2. B only Δf frequency
    3. C only transformer tap without voltage
    4. D only DC link current
    💡 Explanation:

    Corrections added to current θ and V each iteration.

  26. Q26 medium

    Flat start for NR on stiff EHV system may require

    1. A no iteration at all
    2. B better initial voltages or damping to avoid early divergence
    3. C removing all loads
    4. D setting all P to zero
    💡 Explanation:

    Difficult cases need engineering initial guesses or homotopy.

  27. Q27 hard

    Transformer regulating tap change during NR may use

    1. A continuous tap without limits always
    2. B no tap model
    3. C discrete tap steps outer loop around continuous NR
    4. D only mechanical brake model
    💡 Explanation:

    Tap is discrete; outer control adjusts tap after flow solution.

  28. Q28 medium

    Loss allocation after NR can use

    1. A only guess without voltages
    2. B only solar azimuth angle
    3. C only corona RI
    4. D incremental loss factors or proportional sharing methods
    💡 Explanation:

    Loss formulas distribute line losses to generators/loads.

  29. Q29 Past Paper · PPSC/FPSC/NTS easy

    Symmetrical three-phase fault has

    1. A equal fault currents in all phases with zero sequence unaffected if ungrounded
    2. B only single line open
    3. C only DC offset in one phase without AC
    4. D only negative sequence only
    💡 Explanation:

    Balanced fault simplifies to positive sequence network only.

  30. Q30 Past Paper · PPSC/FPSC/NTS medium

    Line-to-line fault (LL) contains

    1. A all three sequences always including zero
    2. B only zero sequence
    3. C positive and negative sequence components without zero sequence if ungrounded
    4. D only DC component
    💡 Explanation:

    LL is unbalanced but lacks zero sequence if system ungrounded.

  31. Q31 Past Paper · PPSC/FPSC/NTS medium

    Sequence impedances Z1, Z2, Z0 are used to

    1. A analyze unbalanced faults via symmetrical components
    2. B only calculate solar fill factor
    3. C only VFD carrier
    4. D only train adhesion
    💡 Explanation:

    Fortescue transformation decouples unbalanced networks.

  32. Q32 Past Paper · PPSC/FPSC/NTS easy

    Fault MVA at a bus equals

    1. A only real load MW
    2. B √3 × kV_line × kA_fault (three-phase basis) or V²/|Zf| in consistent units
    3. C only transformer iron loss
    4. D only cable length
    💡 Explanation:

    Fault level indicates short-circuit severity for breaker rating.

  33. Q33 Past Paper · PPSC/FPSC/NTS medium

    Subtransient reactance Xd″ of synchronous machine governs

    1. A only steady-state thermal limit
    2. B only governor droop only
    3. C only excitation ceiling at steady state
    4. D initial symmetrical short-circuit current contribution
    💡 Explanation:

    Subtransient period has highest AC fault current from machines.

  34. Q34 hard

    Transient reactance Xd′ is relevant for

    1. A only DC time constant of armature
    2. B only long-term steady state only
    3. C fault current decay in first few cycles
    4. D only solar Voc
    💡 Explanation:

    Current transitions from subtransient to transient level.

  35. Q35 Past Paper · PPSC/FPSC/NTS medium

    DC offset component in fault current arises from

    1. A inductance opposing sudden current change making current asymmetric
    2. B only solar irradiance change
    3. C only biomass moisture
    4. D only PWM switching
    💡 Explanation:

    Offset decays with armature L/R time constant.

  36. Q36 Past Paper · PPSC/FPSC/NTS hard

    Breaker making capacity must withstand

    1. A only RMS symmetrical value always
    2. B peak asymmetrical fault current including DC offset
    3. C only load current
    4. D only charging current
    💡 Explanation:

    First-cycle peak can be substantially above symmetrical peak.

  37. Q37 hard

    Percentage DC component for breaker rating considers

    1. A X/R ratio at fault point affecting asymmetry
    2. B only cable colour
    3. C only tower paint
    4. D only motor poles only
    💡 Explanation:

    High X/R yields slower offset decay and higher peak.

  38. Q38 Past Paper · PPSC/FPSC/NTS medium

    Thevenin equivalent at fault bus for fault calculation uses

    1. A only load power factor
    2. B only solar MPP
    3. C prefault voltage and equivalent impedance looking into network
    4. D only train schedule
    💡 Explanation:

    Vth and Zth simplify fault current computation.

  39. Q39 Past Paper · PPSC/FPSC/NTS easy

    Solid fault means fault impedance is

    1. A infinite
    2. B equal to surge impedance only
    3. C equal to load resistance
    4. D zero
    💡 Explanation:

    Bolted fault assumes no additional impedance at fault point.

  40. Q40 Past Paper · PPSC/FPSC/NTS easy

    Post-fault voltage sag severity depends on

    1. A fault level, impedance to fault and prefault voltage
    2. B only solar panel tilt
    3. C only VFD ramp time only
    4. D only train pantograph material only
    💡 Explanation:

    Stiff networks show smaller voltage depression during faults.

  41. Q41 Past Paper · PPSC/FPSC/NTS medium

    Bus impedance matrix (Z-bus) diagonal element Zii gives

    1. A only off-diagonal mutual terms
    2. B driving-point impedance at bus i for fault calculations
    3. C only shunt capacitance
    4. D only motor slip
    💡 Explanation:

    Zii relates voltage at i to current injected at i.

  42. Q42 Past Paper · PPSC/FPSC/NTS medium

    Distance relay measures

    1. A only transformer temperature
    2. B only solar azimuth
    3. C impedance to fault to trip appropriate line section
    4. D only biogas pressure
    💡 Explanation:

    Z = V/I seen by relay estimates fault location.

  43. Q43 medium

    Open conductor fault can cause

    1. A perfect balance always
    2. B only symmetrical fault
    3. C no effect on loads
    4. D unbalance and abnormal voltages on unaffected phases
    💡 Explanation:

    One or two open phases create severe unbalance.

  44. Q44 Past Paper · PPSC/FPSC/NTS medium

    Fault through impedance (e.g., arc) reduces

    1. A voltage at remote buses to zero always
    2. B fault current magnitude compared with solid fault
    3. C need for any protection
    4. D sequence impedance to zero
    💡 Explanation:

    Arc resistance limits current during fault.

  45. Q45 Past Paper · PPSC/FPSC/NTS medium

    Fast decoupled load flow approximates Jacobian by

    1. A ignoring all reactive power
    2. B using only DC analysis forever
    3. C decoupling P-θ and Q-V assuming high X/R lines
    4. D eliminating slack bus
    💡 Explanation:

    B′ and B″ matrices replace full Jacobian for speed.

  46. Q46 hard

    Quadratic convergence of Newton-Raphson near solution means

    1. A error is constant each step
    2. B error squares each iteration when close to root
    3. C divergence always
    4. D linear halving only
    💡 Explanation:

    Good initial guess yields very fast NR convergence.

  47. Q47 Past Paper · PPSC/FPSC/NTS hard

    Jacobian matrix in NR contains partial derivatives of

    1. A power mismatches with respect to voltage angles and magnitudes
    2. B only line resistance
    3. C only train mass
    4. D only biomass moisture
    💡 Explanation:

    J includes ∂P/∂θ, ∂P/∂V, ∂Q/∂θ, ∂Q/∂V blocks.

  48. Q48 Past Paper · PPSC/FPSC/NTS medium

    Newton-Raphson load flow linearizes

    1. A only DC resistance network without angles
    2. B only single-phase DC battery
    3. C power mismatch equations using Taylor expansion and Jacobian
    4. D only corona power loss
    💡 Explanation:

    NR solves ΔF = −J·Δx iteratively.

  49. Q49 hard

    Distributed slack shares

    1. A all loss to one bus only always
    2. B slack bus responsibility among multiple generators by participation factors
    3. C no slack needed ever
    4. D only reactive load at slack
    💡 Explanation:

    Multiple slack generators share imbalance per defined weights.

  50. Q50 Past Paper · PPSC/FPSC/NTS easy

    Stopping criterion for GS typically checks

    1. A only one bus voltage exactly
    2. B only number of lines
    3. C only solar fill factor
    4. D maximum power mismatch below tolerance
    💡 Explanation:

    max|ΔP|,|ΔQ| < ε across buses ends iteration.

  51. Q51 Past Paper · PPSC/FPSC/NTS medium

    Mismatch at a bus in load flow is

    1. A only voltage magnitude without angle
    2. B difference between specified and calculated power injection
    3. C only frequency error
    4. D only transformer iron loss
    💡 Explanation:

    ΔP and ΔQ drive iterative correction toward convergence.

  52. Q52 easy

    Gauss-Seidel is attractive for teaching because

    1. A it never requires iteration
    2. B it solves nonlinear equations in closed form
    3. C algorithm is simple and needs little memory
    4. D it eliminates Y-bus
    💡 Explanation:

    Educational simplicity; less used in large commercial tools than NR.

  53. Q53 Past Paper · PPSC/FPSC/NTS medium

    After GS converges, line flows are computed from

    1. A bus voltages and branch admittances
    2. B only nameplate MVA
    3. C only rotor resistance
    4. D only braking resistor size
    💡 Explanation:

    Sij = Vi(Vi−Vj)Yij* etc. from solved voltages.

  54. Q54 easy

    Number of iterations in GS depends on

    1. A only utility tariff
    2. B only motor poles
    3. C only solar STC
    4. D tolerance, acceleration and network parameters
    💡 Explanation:

    Tighter ε and difficult cases need more passes.

  55. Q55 hard

    Line charging and high R/X ratio can affect GS convergence by

    1. A improving conditioning always
    2. B making equations more ill-conditioned
    3. C eliminating reactive power
    4. D fixing all angles to zero
    💡 Explanation:

    Stiff networks favour Newton or fast decoupled methods.

  56. Q56 medium

    Weakly meshed distribution feeders may converge with GS when

    1. A never under any condition
    2. B only with no loads
    3. C only without slack
    4. D system is not too stiff and initial guess is reasonable
    💡 Explanation:

    GS works for smaller or well-conditioned networks.

  57. Q57 medium

    Gauss-Seidel update for PQ bus uses

    1. A power injection equations solved for new voltage estimate
    2. B only real power ignoring reactive
    3. C only transformer tap without power
    4. D only fault current
    💡 Explanation:

    Bus equations relate specified P,Q to surrounding voltages.

  58. Q58 Past Paper · PPSC/FPSC/NTS hard

    Reactive power limit violation at PV bus during GS iteration requires

    1. A ignoring limits always
    2. B removing slack bus
    3. C switching bus type from PV to PQ temporarily
    4. D setting frequency to zero
    💡 Explanation:

    When Q hits limit, voltage can no longer be held; bus becomes PQ.

  59. Q59 Past Paper · PPSC/FPSC/NTS easy

    Initial voltage guess for GS load flow often sets

    1. A all voltages zero
    2. B random negative magnitudes
    3. C only DC values
    4. D flat start: 1.0 pu angle 0° except slack
    💡 Explanation:

    Flat start is common unless better estimate available.

  60. Q60 Past Paper · PPSC/FPSC/NTS medium

    Convergence of Gauss-Seidel is generally

    1. A slower than Newton-Raphson for large systems
    2. B always faster than NR always
    3. C independent of R/X ratio
    4. D guaranteed in one iteration
    💡 Explanation:

    NR quadratic convergence beats GS linear rate for tight tolerance.

  61. Q61 medium

    Acceleration factor in Gauss-Seidel can

    1. A guarantee divergence always
    2. B eliminate need for slack bus
    3. C speed convergence of voltage iterations
    4. D convert AC to DC
    💡 Explanation:

    Over-relaxation (α > 1) may improve convergence rate.

  62. Q62 Past Paper · PPSC/FPSC/NTS medium

    Gauss-Seidel method solves load flow by

    1. A only Newton Jacobian inversion each step without iteration structure
    2. B successive substitution using updated values immediately
    3. C only DC mesh analysis
    4. D only symmetrical components only without voltages
    💡 Explanation:

    GS uses most recent voltages when updating each bus sequentially.

  63. Q63 Past Paper · PPSC/FPSC/NTS easy

    PQ bus in load flow specifies

    1. A voltage magnitude and angle
    2. B active and reactive power demand P and Q
    3. C only current magnitude
    4. D only frequency deviation
    💡 Explanation:

    Load buses have specified P and Q; V is unknown.

  64. Q64 Past Paper · PPSC/FPSC/NTS easy

    Slack (swing) bus in load flow specifies

    1. A both P and Q fixed always
    2. B only reactive load
    3. C zero voltage reference
    4. D voltage magnitude and angle to balance system power
    💡 Explanation:

    Slack absorbs mismatch in total P and Q generation vs load.

  65. Q65 Past Paper · PPSC/FPSC/NTS easy

    PV bus in load flow specifies

    1. A active power P and voltage magnitude V
    2. B P and Q both fixed
    3. C V and angle both fixed
    4. D Q and angle only
    💡 Explanation:

    PV (generator) bus controls P and V; Q varies to maintain V.

  66. Q66 Past Paper · PPSC/FPSC/NTS easy

    Load-flow study computes

    1. A only transformer no-load loss
    2. B only motor starting current peak
    3. C voltage magnitudes and angles at buses for given generation and load
    4. D only solar MPP only
    💡 Explanation:

    Steady-state power flow balances P and Q at each bus.

  67. Q67 hard

    Phase-shifting transformer introduces in Y-bus

    1. A only real diagonal terms
    2. B complex mutual admittances with angle shift between buses
    3. C no connection between buses
    4. D only DC link
    💡 Explanation:

    PSD flow controllers modify power flow via phase angle injection.

  68. Q68 Past Paper · PPSC/FPSC/NTS medium

    Y-bus symmetry for passive network without phase shifters means

    1. A Y is always diagonal
    2. B Y is always real
    3. C Y has no diagonal terms
    4. D Yij = Yji for corresponding mutual entries
    💡 Explanation:

    Reciprocal network admittance matrix is symmetric.

  69. Q69 medium

    Sparsity techniques in NR exploit

    1. A dense matrix inversion always
    2. B no branch data
    3. C only 2-bus systems
    4. D few nonzero Jacobian entries in large networks
    💡 Explanation:

    Sparse LU factorization reduces memory and CPU.